11908 W EXPOSITION BLVD 90064
Certificate Information: 11908 W EXPOSITION BLVD 90064
- Application / Permit
- 21010-10000-04886
- Plan Check / Job No.
- B21LA17644
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- New 4-story Type VA 27-unit affordable housing apartment building per TOC Tier 4 (3 ELI Units).
- Permit Issued
- Issued on 10/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 10/5/2021 | APPLICANT |
| Green Plans Picked Up | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | KEVIN MORALES |
| Corrections Issued | 10/20/2021 | KEVIN MORALES |
| Quality Review Completed | 10/21/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| Applicant returned to address corrections | 8/23/2022 | KEVIN MORALES |
| Plan Check Approved | 10/20/2022 | KEVIN MORALES |
| Issued | 10/20/2022 | APPLICANT |
| CofO in Progress | 12/5/2024 | DERRICK SPENCER |
| Permit Finaled | 12/5/2024 | HENRY BAGHDASSARIAN |
| CofO Issued | 12/5/2024 | HENRY BAGHDASSARIAN |
| Permit Finaled | 12/5/2024 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 12/1/2021 | KEVIN MORALES |
| Address approval | Cleared | 12/14/2021 | SAUL GARCIA |
| Permit | Cleared | 12/14/2021 | SAUL GARCIA |
| Building over 36-ft | Cleared | 12/15/2021 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 12/15/2021 | SAUL GARCIA |
| Highway dedication | Cleared | 12/21/2021 | RAYMOND MUGAMBWA |
| Trees in Parkway | Cleared | 2/1/2022 | ADALBERTO VERA |
| Density Bonus 12.22.A.31 | Cleared | 6/21/2022 | JAMES MCCARTHY |
| Frnt yard landscape/Water mgmt | Cleared | 6/22/2022 | ANACANY HURTADO |
| Opn space landscape/Water mgmt | Cleared | 6/22/2022 | ANACANY HURTADO |
| Fire Marshal Fire Life Safety | Cleared | 6/30/2022 | OSCAR SALGADO JR |
| Green Code | Cleared | 7/11/2022 | AARON COSTA |
| Specific Plan | Cleared | 8/11/2022 | PEDRO AYALA |
| Specific Plan | Cleared | 8/11/2022 | PEDRO AYALA |
| Low Impact Development | Cleared | 8/17/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/31/2022 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 9/19/2022 | KURT CORRAL |
| DAS Clearance | Cleared | 10/4/2022 | OLLIE CARTER |
| Specific Plan | Cleared | 10/12/2022 | CONNIE CHAUV |
Contact Information
| Architect | Kudelka,, Phillip Roman; Lic. No.: C19548 | , |
| Contractor | Par Construction Inc; Lic. No.: 983593-B | 12319 GREENE AVE LOS ANGELES, CA 90066 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | , |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2022 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/27/2022 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Not Ready for Inspection | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Partial Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 2/9/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/10/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/22/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/22/2023 | Partial Approval | DERRICK SPENCER |
| Wall Anchors | 2/22/2023 | Partial Approval | DERRICK SPENCER |
| Reinforced Concrete Frame | 5/2/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/3/2023 | Approved | DERRICK SPENCER |
| Green Building Rough | 5/24/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 5/24/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 5/24/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 5/30/2023 | Conditional Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 5/31/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 5/31/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Wood Construction | 6/2/2023 | Approved | DERRICK SPENCER |
| Insulation | 6/6/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 6/14/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 6/14/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 7/5/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Wood Frame | 7/5/2023 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 7/10/2023 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 7/10/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Insulation | 7/10/2023 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Approved | DERRICK SPENCER |
| Insulation | 9/20/2023 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 1/9/2024 | Approved | DERRICK SPENCER |
| Insulation | 1/18/2024 | Approved | DERRICK SPENCER |
| Drywall Nailing | 3/7/2024 | Approved | DERRICK SPENCER |
| Green Building Rough | 3/7/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 4/22/2024 | Approved | DERRICK SPENCER |
| Final | 10/28/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/28/2024 | Approved | DERRICK SPENCER |
| Green Building Final | 10/28/2024 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 10/28/2024 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 10/28/2024 | Approved | DERRICK SPENCER |
| Wood Frame | 10/28/2024 | Approved | DERRICK SPENCER |
| Final | 11/20/2024 | OK to Issue CofO | DERRICK SPENCER |