11908 W EXPOSITION BLVD 90064

Certificate Information: 11908 W EXPOSITION BLVD 90064

Application / Permit
21010-10000-04886
Plan Check / Job No.
B21LA17644
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 4-story Type VA 27-unit affordable housing apartment building per TOC Tier 4 (3 ELI Units).
Permit Issued
Issued on 10/20/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Disabled Access Plans Picked Up 10/5/2021 APPLICANT
Green Plans Picked Up 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 KEVIN MORALES
Corrections Issued 10/20/2021 KEVIN MORALES
Quality Review Completed 10/21/2021 EUGENE BARBEAU
Building Plans Picked Up 10/26/2021 APPLICANT
Applicant returned to address corrections 8/23/2022 KEVIN MORALES
Plan Check Approved 10/20/2022 KEVIN MORALES
Issued 10/20/2022 APPLICANT
CofO in Progress 12/5/2024 DERRICK SPENCER
Permit Finaled 12/5/2024 HENRY BAGHDASSARIAN
CofO Issued 12/5/2024 HENRY BAGHDASSARIAN
Permit Finaled 12/5/2024 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Metro Rail approval Cleared 12/1/2021 KEVIN MORALES
Address approval Cleared 12/14/2021 SAUL GARCIA
Permit Cleared 12/14/2021 SAUL GARCIA
Building over 36-ft Cleared 12/15/2021 CALOSHA APPROVED
Eng Process Fee Ord 176,300 Cleared 12/15/2021 SAUL GARCIA
Sewer availability Cleared 12/15/2021 SAUL GARCIA
Highway dedication Cleared 12/21/2021 RAYMOND MUGAMBWA
Trees in Parkway Cleared 2/1/2022 ADALBERTO VERA
Density Bonus 12.22.A.31 Cleared 6/21/2022 JAMES MCCARTHY
Frnt yard landscape/Water mgmt Cleared 6/22/2022 ANACANY HURTADO
Opn space landscape/Water mgmt Cleared 6/22/2022 ANACANY HURTADO
Fire Marshal Fire Life Safety Cleared 6/30/2022 OSCAR SALGADO JR
Green Code Cleared 7/11/2022 AARON COSTA
Specific Plan Cleared 8/11/2022 PEDRO AYALA
Specific Plan Cleared 8/11/2022 PEDRO AYALA
Low Impact Development Cleared 8/17/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/31/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 9/19/2022 KURT CORRAL
DAS Clearance Cleared 10/4/2022 OLLIE CARTER
Specific Plan Cleared 10/12/2022 CONNIE CHAUV

Contact Information

Architect Kudelka,, Phillip Roman; Lic. No.: C19548       ,
Contractor Par Construction Inc; Lic. No.: 983593-B 12319 GREENE AVE      LOS ANGELES, CA 90066
Engineer Funk,, David Lyle; Lic. No.: S5421       ,

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 12/27/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 12/27/2022 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 12/28/2022 Not Ready for Inspection DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 2/9/2023 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 2/9/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/10/2023 Conditional Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/22/2023 Conditional Approval DERRICK SPENCER
Footing/Foundation/Slab 2/22/2023 Partial Approval DERRICK SPENCER
Wall Anchors 2/22/2023 Partial Approval DERRICK SPENCER
Reinforced Concrete Frame 5/2/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 5/3/2023 Approved DERRICK SPENCER
Green Building Rough 5/24/2023 Not Ready for Inspection DERRICK SPENCER
Verify Sprinkler Sign Off 5/24/2023 Approved DERRICK SPENCER
Wood Frame 5/24/2023 Partial Approval DERRICK SPENCER
Deputy Wood Construction 5/30/2023 Conditional Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval DERRICK SPENCER
Green Building Rough 5/31/2023 Not Ready for Inspection DERRICK SPENCER
Wood Frame 5/31/2023 Partial Approval DERRICK SPENCER
Deputy Wood Construction 6/2/2023 Approved DERRICK SPENCER
Insulation 6/6/2023 Partial Approval DERRICK SPENCER
Green Building Rough 6/14/2023 Not Ready for Inspection DERRICK SPENCER
Wood Frame 6/14/2023 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval DERRICK SPENCER
Green Building Rough 7/5/2023 Not Ready for Inspection DERRICK SPENCER
Wood Frame 7/5/2023 Partial Approval DERRICK SPENCER
Drywall Nailing 7/10/2023 Partial Approval DERRICK SPENCER
Green Building Rough 7/10/2023 Not Ready for Inspection DERRICK SPENCER
Insulation 7/10/2023 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Approved DERRICK SPENCER
Insulation 9/20/2023 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 1/9/2024 Approved DERRICK SPENCER
Insulation 1/18/2024 Approved DERRICK SPENCER
Drywall Nailing 3/7/2024 Approved DERRICK SPENCER
Green Building Rough 3/7/2024 Approved DERRICK SPENCER
Pre-Inspection 4/22/2024 Approved DERRICK SPENCER
Final 10/28/2024 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 10/28/2024 Approved DERRICK SPENCER
Green Building Final 10/28/2024 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Approved DERRICK SPENCER
Smoke Detectors 10/28/2024 Approved DERRICK SPENCER
Wood Frame 10/28/2024 Approved DERRICK SPENCER
Final 11/20/2024 OK to Issue CofO DERRICK SPENCER