1012 W 21ST ST 90007
Certificate Information: 1012 W 21ST ST 90007
- Application / Permit
- 21010-10000-04879
- Plan Check / Job No.
- B21LA17618
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ADU WITH ATTACHED 4-CAR GARAGE PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/29/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/9/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| Plan Check Approved | 1/24/2023 | MAHNAZ NOURHASHEMI |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 1/8/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
| CofO Issued | 1/9/2025 | DEROLD HAUFF |
| Permit Finaled | 1/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/6/2022 | JULIAN SUNG |
| Address approval | Cleared | 6/9/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | TREVOR QUAN |
| HPOZ | Cleared | 6/14/2022 | LAMBERT GIESSINGER |
| Hist. Property Cntrct Mgr Appr | Cleared | 6/14/2022 | LAMBERT GIESSINGER |
| Hydrant and Access approval | Cleared | 8/26/2022 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 9/7/2022 | TREVOR QUAN |
| "Q" conditions | Cleared | 9/8/2022 | KENTON TRINH |
| ZI | Cleared | 9/8/2022 | KENTON TRINH |
| Trees in Parkway | Cleared | 10/28/2022 | ADALBERTO VERA |
| Permit | Cleared | 11/3/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 3/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 3/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 3/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 3/20/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/3/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| MERV13>=Rough | 5/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Rough | 5/1/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/1/2024 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 5/1/2024 | Partial Approval | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 5/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/13/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/17/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 5/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 5/28/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 5/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 11/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/3/2025 | Corrections Issued | ENRIQUE MIRELES |
| Final | 1/7/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |