1452 W 84TH PL 90047

Certificate Information: 1452 W 84TH PL 90047

Application / Permit
21010-10000-04878
Plan Check / Job No.
B21LA17605
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH 6-CAR GARAGE
Permit Issued
Issued on 5/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 DANIEL YIP
Corrections Issued 10/13/2021 DANIEL YIP
Quality Review Completed 10/21/2021 ALLEN MANALANSAN
Building Plans Picked Up 10/25/2021 APPLICANT
Plan Check Approved 1/14/2022 DANIEL YIP
Issued 5/27/2022 APPLICANT
CofO in Progress 12/1/2022 LILIANA PORTILLO
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/8/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 11/9/2021 CINDY QI
Frnt yard landscape/Water mgmt Cleared 11/9/2021 LOUIS ORTEGA
Sewer availability Cleared 11/9/2021 CINDY QI
Hydrant and Access approval Cleared 11/12/2021 ROBERT DUFF
Tenant Habitability Plan Cleared 12/17/2021 MICHAEL SOTO
Low Impact Development Cleared 1/12/2022 CHRIS PARK
Roof/Waste drainage to street Cleared 1/12/2022 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 8/26/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 8/26/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Approved LILIANA PORTILLO
Green Building Rough 8/26/2022 Approved LILIANA PORTILLO
HVAC-Rough 8/26/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 8/26/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 8/26/2022 Approved LILIANA PORTILLO
Insulation 8/30/2022 Approved LILIANA PORTILLO
Drywall Nailing 9/9/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 9/9/2022 Approved LILIANA PORTILLO
Sewer 9/30/2022 Approved LILIANA PORTILLO
Underground Mechanical 9/30/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/8/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/9/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 11/23/2022 Not Ready for Inspection LILIANA PORTILLO
Final 11/23/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 11/23/2022 Approved LILIANA PORTILLO
HVAC-Final 11/23/2022 Approved LILIANA PORTILLO
PLUMBING-Final 11/23/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 11/23/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 11/23/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/28/2022 Approved LILIANA PORTILLO
Final 11/28/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 11/28/2022 Approved LILIANA PORTILLO
Service/Power Release 11/30/2022 Approved LILIANA PORTILLO