2260 S PROSSER AVE 90064
Certificate Information: 2260 S PROSSER AVE 90064
- Application / Permit
- 21010-10000-04869
- Plan Check / Job No.
- B21LA17574
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | CARLOS MONTES |
| Corrections Issued | 10/18/2021 | CARLOS MONTES |
| Quality Review Completed | 10/21/2021 | KEN GILL |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| Applicant returned to address corrections | 2/23/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 4/5/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 9/21/2022 | CARLOS MONTES |
| Plan Check Approved | 10/5/2022 | CARLOS MONTES |
| Issued | 10/12/2022 | APPLICANT |
| CofO in Progress | 12/17/2025 | DANIEL VERA |
| CofO in Progress | 12/17/2025 | DANIEL VERA |
| CofO in Progress | 12/26/2025 | DANIEL VERA |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hold | Cleared | 10/12/2021 | JASON SHEETS |
| Grading Pre-Inspection | Cleared | 1/27/2022 | ROBERT HUGHES |
| Address approval | Cleared | 3/24/2022 | DINAH GARIN |
| Specific Plan | Cleared | 3/30/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 4/1/2022 | SUNG JOON WON |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/6/2022 | DINAH GARIN |
| Sewer availability | Cleared | 4/6/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/20/2022 | GREGORY HOERNER |
| Flood clearance | Cleared | 9/12/2022 | BRYAN GATHUKA |
| GPI Written Notices | Cleared | 9/20/2022 | CARLOS MONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2022 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 5/2/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Partial Approval | BRENDAN LOONEY |
| Deputy Steel/Welding | 6/7/2023 | Conditional Approval | MICHAEL PELHAM |
| FLOOD-Elevation Certificate | 6/13/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/13/2023 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 6/27/2023 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Wood Frame | 6/28/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 7/12/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 8/17/2023 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Partial Approval | MICHAEL PELHAM |
| HVAC-Rough | 10/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 11/16/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 11/29/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/30/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/30/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 1/30/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/30/2024 | Conditional Approval | STEPHANIE SWANSON |
| Shower Pan | 1/30/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 2/5/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/14/2024 | Partial Approval | STEPHANIE SWANSON |
| FLOOD-Proofing Certificate | 2/14/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 2/14/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 2/14/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 2/14/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 3/27/2024 | Approved | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 5/28/2024 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 5/28/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 6/14/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/22/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 6/9/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 7/11/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 7/23/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 7/23/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 7/23/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 7/23/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Final | 8/8/2025 | Approved | DANIEL VERA |
| HVAC-Final | 8/8/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | DANIEL VERA |
| Final | 11/14/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 11/14/2025 | Approved | DANIEL VERA |
| METHANE-Final | 11/14/2025 | Approved | DANIEL VERA |
| METHANE-Rough | 11/14/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Not Required | DANIEL VERA |
| Service/Power Release | 11/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 11/14/2025 | Approved | DANIEL VERA |
| Structural Steel Frame | 11/14/2025 | Approved | DANIEL VERA |
| Final | 12/2/2025 | Corrections Issued | SEAN HAUPT |
| Service/Power Release | 12/2/2025 | Not Ready for Inspection | SEAN HAUPT |
| Pre-Inspection | 12/4/2025 | Approved | DANIEL VERA |
| Final | 12/15/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 12/16/2025 | Conditional Approval | DANIEL VERA |
| Service/Power Release | 12/16/2025 | Approved | DANIEL VERA |
| Final | 12/24/2025 | OK to Issue CofO | DANIEL VERA |