1048 W 84TH ST 90044

Certificate Information: 1048 W 84TH ST 90044

Application / Permit
21010-10000-04860
Plan Check / Job No.
B21LA17505
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD (FRONT LOT).
Permit Issued
Issued on 5/18/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 MAHNAZ NOURHASHEMI
Corrections Issued 10/28/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 11/5/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/8/2021 APPLICANT
Applicant returned to address corrections 1/24/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 2/3/2023 MAHNAZ NOURHASHEMI
No Progress 2/3/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 5/18/2023 MAHNAZ NOURHASHEMI
Issued 5/18/2023 APPLICANT
CofO in Progress 2/20/2024 MICHAEL LEWIS
Permit Finaled 2/22/2024 DEROLD HAUFF
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/23/2021 CINDY QI
Low Impact Development Cleared 1/14/2022 SUNG JOON WON
Hydrant and Access approval Cleared 5/12/2022 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 1/20/2023 CINDY QI
Sewer availability Cleared 1/20/2023 CINDY QI
Roof/Waste drainage to street Cleared 2/2/2023 CINDY QI
Frnt yard landscape/Water mgmt Cleared 3/24/2023 JAZMIN ROQUE

Contact Information

Architect Kelly,, Jonathan Stanleigh; Lic. No.: C34283 4153 S HARVARD BLVD      LOS ANGELES, CA 90062
Contractor Aardvark Group Inc The; Lic. No.: 762498-B 13337 SOUTH STREET # 134      CERRITOS, CA 90703
Engineer Liu,, Joseph; Lic. No.: C60045 825 S GOLDEN WEST AVE 9      ARCADIA, CA 91007

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/13/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 6/21/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 6/21/2023 Approved MICHAEL LEWIS
Sewer 6/28/2023 Approved MICHAEL LEWIS
Underground Mechanical 6/28/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/6/2023 Approved MICHAEL LEWIS
HVAC-Rough 9/6/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 9/6/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/18/2023 Corrections Issued MICHAEL LEWIS
Green Building Rough 9/18/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 9/18/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/20/2023 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 9/27/2023 Conditional Approval MICHAEL LEWIS
Insulation 9/27/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 9/27/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/12/2023 Approved MICHAEL LEWIS
Gas Test 1/23/2024 Approved MICHAEL LEWIS
PLUMBING-Final 1/23/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 1/29/2024 Partial Approval MICHAEL LEWIS
HVAC-Final 1/29/2024 Approved MICHAEL LEWIS
Service/Power Release 1/29/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/30/2024 Approved MICHAEL LEWIS
Final 1/30/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 1/30/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 1/30/2024 Approved MICHAEL LEWIS
Smoke Detectors 1/30/2024 Approved MICHAEL LEWIS
Final 2/15/2024 OK to Issue CofO MICHAEL LEWIS