8938 W GIBSON ST 90034
Certificate Information: 8938 W GIBSON ST 90034
- Application / Permit
- 21010-10000-04850
- Plan Check / Job No.
- B21LA17470
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert existing garage and new addition to new ADU
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2021 | HERNAN ARREOLA |
| Corrections Issued | 9/20/2021 | HERNAN ARREOLA |
| Plan Check Approved | 5/16/2022 | HERNAN ARREOLA |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 7/14/2023 | ARAM AVEDISIAN |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
| CofO Issued | 7/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/14/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 3/23/2022 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Pacific Grand Builders Inc; Lic. No.: 695424-B | P O BOX 341518 LOS ANGELES, CA 90034 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/15/2022 | Partial Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 9/8/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/30/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/21/2022 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/21/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 10/21/2022 | Partial Approval | EVAN COOPER |
| Sewer | 10/21/2022 | Approved | EVAN COOPER |
| Wood Frame | 10/21/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 11/7/2022 | Partial Approval | EVAN COOPER |
| Shower Pan | 11/7/2022 | Approved | EVAN COOPER |
| Wood Frame | 11/7/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 11/14/2022 | Approved | MICHAEL PELHAM |
| Insulation | 11/14/2022 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 11/14/2022 | Approved | MICHAEL PELHAM |
| Drywall Nailing | 11/22/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 11/22/2022 | Partial Inspection | JEREMY TODD |
| Interior/Exterior Lathing | 2/22/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Final | 4/20/2023 | Approved | JEREMY TODD |
| HVAC-Final | 4/20/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 4/20/2023 | Approved | JEREMY TODD |
| Pre-Inspection | 4/20/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 7/5/2023 | Approved | ARAM AVEDISIAN |
| Final | 7/5/2023 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV No Gas | ARAM AVEDISIAN |
| Smoke Detectors | 7/5/2023 | Approved | ARAM AVEDISIAN |
| Final | 7/14/2023 | OK to Issue CofO | ARAM AVEDISIAN |