4419 3/4 S METTLER ST 90011

Certificate Information: 4419 3/4 S METTLER ST 90011

Application / Permit
21010-10000-04845
Plan Check / Job No.
B21LA17426
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2 STORY ADU AT REAR OF LOT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 11/6/2025
Issuing Office
Metro
Current Status
Issued on 11/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 VIVIAN LAO
Corrections Issued 10/28/2021 VIVIAN LAO
Quality Review Completed 11/5/2021 GARO TELMI
Building Plans Picked Up 11/29/2021 APPLICANT
Applicant returned to address corrections 4/13/2023 VIVIAN LAO
Plan Check Approved 4/18/2023 VIVIAN LAO
Issued 11/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/16/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/23/2022 CINDY QI
Sewer availability Cleared 6/23/2022 CINDY QI
Hydrant and Access approval Cleared 11/9/2022 KURT CORRAL
Low Impact Development Cleared 4/10/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/14/2023 CINDY QI

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/12/2026 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/12/2026 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/22/2026 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/18/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/31/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/1/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/2/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/6/2026 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 4/6/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/6/2026 Partial Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/6/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/13/2026 Approved ALEJANDRO DE ARTOLA
Insulation 4/13/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 4/14/2026 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 4/22/2026 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/22/2026 Partial Approval ALEJANDRO DE ARTOLA
Final 4/30/2026 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 5/29/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 5/29/2026 Approved ALEJANDRO DE ARTOLA
Gas Test 6/1/2026 Partial Approval ALEJANDRO DE ARTOLA
Sewer 6/1/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/1/2026 Corrections Issued ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 6/1/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/8/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/12/2026 Corrections Issued ALEJANDRO DE ARTOLA