2119 S WEST VIEW ST 90016
Certificate Information: 2119 S WEST VIEW ST 90016
- Application / Permit
- 21010-10000-04822
- Plan Check / Job No.
- B21LA17341
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE AT FRONT OF LOT
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | PRANITA SHAH |
| Corrections Issued | 11/4/2021 | PRANITA SHAH |
| Quality Review Completed | 11/16/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 11/18/2021 | APPLICANT |
| Applicant returned to address corrections | 4/15/2022 | PRANITA SHAH |
| Plan Check Approved | 5/18/2022 | PRANITA SHAH |
| Issued | 6/1/2022 | APPLICANT |
| CofO in Progress | 7/15/2024 | STUART CHAPMAN |
| Permit Finaled | 7/15/2024 | DEROLD HAUFF |
| CofO Issued | 7/15/2024 | DEROLD HAUFF |
| Permit Finaled | 7/15/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2021 | CINDY QI |
| Highway dedication | Cleared | 11/23/2021 | CINDY QI |
| Permit | Cleared | 11/23/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | CINDY QI |
| Sewer availability | Cleared | 11/24/2021 | CINDY QI |
| Frnt yard landscape/Water mgmt | Cleared | 12/22/2021 | ANACANY HURTADO |
| Trees in Parkway | Cleared | 1/6/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 2/14/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/24/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | AMAAN MALIK |
| Hold | Cleared | 7/15/2022 | JASON SHEETS |
Contact Information
| Contractor | Alpha Build & Design Inc; Lic. No.: 398659-B | 611 WILSHIRE BLVD #1416 LOS ANGELES, CA 90017 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 7/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 9/15/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 9/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 9/27/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 9/27/2022 | Corrections Issued | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/11/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/12/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 11/2/2022 | Conditional Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 12/29/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 1/23/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 2/1/2023 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 2/8/2023 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 2/8/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 2/14/2023 | Approved | CALEB MEISTER |
| Deputy Wood Construction | 2/23/2023 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/24/2023 | No Access for Inspection | CALEB MEISTER |
| HVAC-Rough | 2/24/2023 | No Access for Inspection | CALEB MEISTER |
| Deputy Wood Construction | 3/7/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 3/8/2023 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 3/8/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | CALEB MEISTER |
| Green Building Rough | 3/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 3/16/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 3/16/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 4/19/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 4/19/2023 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 5/10/2023 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 5/23/2023 | Conditional Approval | CALEB MEISTER |
| Green Building Rough | 5/23/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 5/23/2023 | Approved | CALEB MEISTER |
| Wood Frame | 5/23/2023 | Approved | CALEB MEISTER |
| Insulation | 6/2/2023 | Corrections Issued | CALEB MEISTER |
| Shower Pan | 6/6/2023 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 6/12/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/20/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 6/23/2023 | Approved | CALEB MEISTER |
| Shower Pan | 6/23/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 10/4/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Sewer | 10/4/2023 | Partial Inspection | STUART CHAPMAN |
| Underground Mechanical | 10/4/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 10/6/2023 | Approved | CALEB MEISTER |
| Sewer | 10/6/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 10/6/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 10/25/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 11/21/2023 | No Access for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/12/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/12/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 2/12/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 2/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 2/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/12/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/12/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/26/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/28/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 2/28/2024 | Corrections Issued | JUSTIN HAWLEY |
| Service/Power Release | 2/28/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/4/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Final | 3/4/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 3/4/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Final | 3/21/2024 | Corrections Issued | STUART CHAPMAN |
| Final | 3/21/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 3/21/2024 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Final | 3/21/2024 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 3/27/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 3/27/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 3/27/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/27/2024 | Corrections Issued | JUSTIN HAWLEY |
| MERV13>=Final | 3/27/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/27/2024 | Approved | JUSTIN HAWLEY |
| Final | 5/7/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/15/2024 | Approved | STUART CHAPMAN |
| Final | 7/15/2024 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 7/15/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 7/15/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 7/15/2024 | Approved | STUART CHAPMAN |