6522-6524 S DENVER AVE 90044

Certificate Information: 6522-6524 S DENVER AVE 90044

Application / Permit
21010-10000-04818
Plan Check / Job No.
B21LA17329
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT AND 2-CAR GARAGE AT REAR
Permit Issued
Issued on 1/6/2022
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SERGIO GUTIERREZ
Corrections Issued 10/14/2021 SERGIO GUTIERREZ
Quality Review Completed 10/15/2021 FARUK SEZER
Plan Check Approved 12/3/2021 SERGIO GUTIERREZ
Issued 1/6/2022 APPLICANT
Building Plans Picked Up 1/10/2022 APPLICANT
CofO in Progress 8/18/2022 ALEJANDRO DE ARTOLA
Permit Finaled 8/25/2022 DEROLD HAUFF
CofO Issued 8/25/2022 DEROLD HAUFF
Permit Finaled 8/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 10/25/2021 LONDY ALVARADO
Hydrant and Access approval Cleared 11/5/2021 ROBERT DUFF
Roof/Waste drainage to street Cleared 11/9/2021 CELINA MORENO
Address approval Cleared 11/12/2021 CELINA MORENO
Permit Cleared 11/12/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/15/2021 CELINA MORENO
Sewer availability Cleared 11/15/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/16/2022 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/16/2022 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 2/18/2022 Conditional Approval JOAQUIN GREENOUGH
Pre-Inspection 3/1/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/2/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 3/2/2022 Partial Approval LILIANA PORTILLO
Sewer 3/2/2022 Approved LILIANA PORTILLO
Underground Mechanical 3/2/2022 Approved LILIANA PORTILLO
Insulation 3/3/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval LILIANA PORTILLO
Deputy Wood Construction 4/21/2022 No Access for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 5/5/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/5/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/6/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 5/6/2022 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 5/6/2022 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 5/6/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 5/9/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 5/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 5/13/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/16/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 5/16/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/17/2022 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/18/2022 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/23/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/25/2022 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/8/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/15/2022 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/29/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 7/29/2022 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 8/3/2022 Approved ALEJANDRO DE ARTOLA
Final 8/3/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 8/3/2022 Approved ALEJANDRO DE ARTOLA
Green Building Final 8/3/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 8/3/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 8/3/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 8/3/2022 Approved ALEJANDRO DE ARTOLA
Service/Power Release 8/3/2022 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 8/3/2022 Approved ALEJANDRO DE ARTOLA
Final 8/4/2022 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 8/4/2022 Approved ALEJANDRO DE ARTOLA
Final 8/17/2022 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 8/17/2022 Approved ALEJANDRO DE ARTOLA