4883 N RUTH AVE 90041
Certificate Information: 4883 N RUTH AVE 90041
- Application / Permit
- 21010-10000-04814
- Plan Check / Job No.
- B21LA17316
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1 STORY DETACHED ACCESSORY DWELLING UNIT (ADU)
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | JOE VO |
| Corrections Issued | 9/17/2021 | JOE VO |
| Applicant returned to address corrections | 11/9/2021 | JOE VO |
| Plan Check Approved | 1/25/2022 | JOE VO |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 1/12/2023 | CRAIG VAUGHAN |
| CofO Issued | 1/18/2023 | DEROLD HAUFF |
| Permit Finaled | 1/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 9/29/2021 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 10/15/2021 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | PAMELA TENEZA |
| Sewer availability | Cleared | 11/16/2021 | PAMELA TENEZA |
| Miscellaneous | Cleared | 1/24/2022 | ALBERT TAM |
Contact Information
| Contractor | Omar Construction; Lic. No.: 1053510-B | 4217 WHEELER STREET RIVERSIDE, CA 92503 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/21/2022 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/12/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 8/12/2022 | Conditional Approval | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 8/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/15/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/17/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 8/17/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/26/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/26/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/26/2022 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/29/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Wood Frame | 8/29/2022 | No Access for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/1/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 9/1/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 9/1/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/1/2022 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 9/1/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/7/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 9/7/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/7/2022 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 9/26/2022 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 9/30/2022 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 9/30/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 9/30/2022 | Corrections Issued | CRAIG VAUGHAN |
| Sewer | 9/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 9/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 10/5/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 11/15/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 12/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 12/28/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Required | CRAIG VAUGHAN |
| Service/Power Release | 12/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 12/28/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/3/2023 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 1/3/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/3/2023 | Approved | CRAIG VAUGHAN |
| Final | 1/5/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/5/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/11/2023 | Approved | CRAIG VAUGHAN |
| Final | 1/11/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 1/11/2023 | Approved | CRAIG VAUGHAN |