7040 S 7TH AVE 90043

Certificate Information: 7040 S 7TH AVE 90043

Application / Permit
21010-10000-04810
Plan Check / Job No.
B21LA17307
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU WITH AN ADDITION, DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/20/2021 CARLOS MONTES
Corrections Issued 9/20/2021 CARLOS MONTES
Applicant returned to address corrections 11/5/2021 CARLOS MONTES
Applicant returned to address corrections 12/13/2021 CARLOS MONTES
Applicant returned to address corrections 12/27/2021 CARLOS MONTES
Applicant returned to address corrections 1/5/2022 CARLOS MONTES
Applicant returned to address corrections 2/3/2022 CARLOS MONTES
Applicant returned to address corrections 2/8/2022 CARLOS MONTES
Plan Check Approved 2/25/2022 CARLOS MONTES
Issued 5/11/2022 APPLICANT
CofO in Progress 10/23/2023 ENRIQUE MIRELES
CofO in Progress 10/23/2023 ENRIQUE MIRELES
Permit Finaled 11/3/2023 DEROLD HAUFF
CofO Issued 11/3/2023 DEROLD HAUFF
Permit Finaled 11/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/6/2021 CINDY QI
Roof/Waste drainage to street Cleared 12/6/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/9/2021 CINDY QI
Sewer availability Cleared 12/9/2021 CINDY QI
Construction near power lines Cleared 2/16/2022 TORI CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Saleh,, Zouheir Toufic; Lic. No.: C42881 1304 CORTE MALTERA      COSTA MESA, CA 92626

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/15/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/21/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/21/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 7/21/2023 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 7/24/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/28/2023 Partial Approval ENRIQUE MIRELES
Insulation 8/2/2023 Partial Approval ENRIQUE MIRELES
BUILDING-Rough-Frame 8/7/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 8/7/2023 Approved ENRIQUE MIRELES
Green Building Rough 8/7/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/7/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/14/2023 Approved ENRIQUE MIRELES
Insulation 8/21/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/21/2023 Approved ENRIQUE MIRELES
Drywall Nailing 8/30/2023 Approved ENRIQUE MIRELES
Final 10/10/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 10/10/2023 Approved ENRIQUE MIRELES
Final 10/16/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/16/2023 Approved ENRIQUE MIRELES
Final 10/19/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 10/20/2023 Approved ENRIQUE MIRELES