Permit Issued
Issued on 7/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 KHEDER ALRAZAA
Corrections Issued 10/28/2021 KHEDER ALRAZAA
Quality Review Completed 11/5/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/10/2021 APPLICANT
Applicant returned to address corrections 12/21/2021 KHEDER ALRAZAA
Applicant returned to address corrections 5/25/2022 KHEDER ALRAZAA
Plan Check Approved 6/15/2022 KHEDER ALRAZAA
Issued 7/13/2022 APPLICANT
CofO in Progress 9/12/2024 JEFFREY MEAD
Permit Finaled 1/8/2025 DEROLD HAUFF
CofO Issued 1/8/2025 DEROLD HAUFF
Permit Finaled 1/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/5/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/15/2021 JEANIE LAM
Sewer availability Cleared 11/15/2021 JEANIE LAM
Hydrant and Access approval Cleared 12/27/2021 GILBERT URREA
Frnt yard landscape/Water mgmt Cleared 5/9/2022 DALIA MOKAYED
Low Impact Development Cleared 5/18/2022 TA ANH
Roof/Waste drainage to street Cleared 5/18/2022 JEANIE LAM

Contact Information

Contractor Inhance Construction Inc; Lic. No.: 1073871-B 7257 BEVERLY RD STE 205      LOS ANGELES, CA 90036

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/11/2022 Approved JEFFREY MEAD
Underground Mechanical 10/11/2022 Approved JEFFREY MEAD
Deputy Methane Barrier 10/14/2022 No Access for Inspection JEFFREY MEAD
Underground Mechanical 10/14/2022 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 10/31/2022 Approved JEFFREY MEAD
Deputy Reinf. Concrete 11/1/2022 Partial Approval JEFFREY MEAD
Deputy Methane Barrier 11/15/2022 Approved JEFFREY MEAD
METHANE-Rough 11/15/2022 Approved JEFFREY MEAD
Deputy Methane Barrier 11/17/2022 Partial Approval JEFFREY MEAD
METHANE-Barrier 11/17/2022 Approved JEFFREY MEAD
Deputy Methane Barrier 11/18/2022 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 11/21/2022 Approved JEFFREY MEAD
Deputy Reinf. Concrete 11/28/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 11/29/2022 Approved JEFFREY MEAD
Deputy Reinf. Concrete 12/1/2022 Partial Approval JEFFREY MEAD
Sewer 12/8/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 No Access for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval JEFFREY MEAD
Underground Mechanical 5/3/2023 Partial Approval JEFFREY MEAD
Underground Mechanical 6/1/2023 Approved JEFFREY MEAD
Deputy Wood Construction 7/18/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 9/1/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 9/1/2023 Approved JEFFREY MEAD
Gas Test 9/6/2023 Approved JEFFREY MEAD
HVAC-Rough 9/6/2023 Approved JEFFREY MEAD
PLUMBING-Rough 9/6/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 9/18/2023 Corrections Issued JEFFREY MEAD
Green Building Rough 9/18/2023 Approved JEFFREY MEAD
MERV13>=Rough 9/18/2023 Approved JEFFREY MEAD
Shower Pan 9/18/2023 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 9/18/2023 Approved JEFFREY MEAD
Deputy Methane Barrier 9/20/2023 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval JEFFREY MEAD
Insulation 9/27/2023 Approved JEFFREY MEAD
METHANE-Final 9/27/2023 Approved JEFFREY MEAD
Drywall Nailing 10/5/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/5/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 5/8/2024 Approved JEFFREY MEAD
Gas Test 5/8/2024 Approved JEFFREY MEAD
PLUMBING-Final 5/8/2024 Approved JEFFREY MEAD
Drywall Nailing 5/17/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 8/15/2024 Corrections Issued BRENDAN MORELLI
HVAC-Final 8/15/2024 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 8/20/2024 Corrections Issued JEFFREY MEAD
HVAC-Final 8/20/2024 Approved JEFFREY MEAD
Service/Power Release 8/20/2024 Not Ready for Inspection JEFFREY MEAD
Final 9/9/2024 Corrections Issued JEFFREY MEAD
Green Building Final 9/9/2024 Approved JEFFREY MEAD
MERV13>=Final 9/9/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved JEFFREY MEAD
Service/Power Release 9/9/2024 Not Required JEFFREY MEAD
Smoke Detectors 9/9/2024 Approved JEFFREY MEAD
Final 9/12/2024 OK to Issue CofO JEFFREY MEAD
Service/Power Release 9/12/2024 Not Required JEFFREY MEAD