331-331 1/2 E 64TH ST 90003

Certificate Information: 331-331 1/2 E 64TH ST 90003

Application / Permit
21010-10000-04750
Plan Check / Job No.
B21LA17090
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED GARAGE (NFPA 13D THRU OUT)
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 AUNG SOE
Corrections Issued 10/7/2021 AUNG SOE
Quality Review Completed 10/12/2021 EUGENE BARBEAU
Building Plans Picked Up 10/14/2021 APPLICANT
Applicant returned to address corrections 1/31/2022 AUNG SOE
Plan Check Approved 2/3/2022 AUNG SOE
Issued 10/14/2022 APPLICANT
CofO in Progress 4/6/2023 ALEJANDRO DE ARTOLA
Permit Finaled 4/11/2023 DEROLD HAUFF
CofO Issued 4/11/2023 DEROLD HAUFF
Permit Finaled 4/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/26/2021 CHRISTOPHER ROCHA
Permit Cleared 10/26/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 11/5/2021 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 11/5/2021 ROBERT DUFF
Trees in Parkway Cleared 1/25/2022 ADALBERTO VERA
Low Impact Development Cleared 1/27/2022 TA ANH
Roof/Waste drainage to street Cleared 1/28/2022 CELINA MORENO
Sewer availability Cleared 1/28/2022 CHRISTOPHER ROCHA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/7/2022 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/7/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval LILIANA PORTILLO
Insulation 12/8/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 1/19/2023 Approved LILIANA PORTILLO
HVAC-Rough 1/19/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 1/20/2023 Approved LILIANA PORTILLO
Green Building Rough 1/20/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 1/20/2023 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 1/20/2023 Approved LILIANA PORTILLO
Insulation 1/23/2023 Approved LILIANA PORTILLO
Drywall Nailing 2/1/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 2/1/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 3/16/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Final 4/4/2023 Approved ALEJANDRO DE ARTOLA
Final 4/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/4/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/4/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/4/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 4/4/2023 Approved ALEJANDRO DE ARTOLA
Final 4/5/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
PLUMBING-Final 4/5/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/5/2023 Approved ALEJANDRO DE ARTOLA