131-133 E 57TH ST 90011
Certificate Information: 131-133 E 57TH ST 90011
- Application / Permit
- 21010-10000-04745
- Plan Check / Job No.
- B21LA17067
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE.
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 11/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | MICHAEL LOPEZ |
| Corrections Issued | 10/7/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 10/13/2021 | KEN GILL |
| Plan Check Approved | 1/10/2022 | MICHAEL LOPEZ |
| Issued | 2/8/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 10/20/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/10/2022 | DEROLD HAUFF |
| Permit Finaled | 11/10/2022 | DEROLD HAUFF |
| CofO Issued | 11/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 10/22/2021 | JASON CHAN |
| Address approval | Cleared | 10/27/2021 | AMAAN MALIK |
| Permit | Cleared | 10/27/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 10/28/2021 | CHRISTOPHER ROCHA |
| Trees in Parkway | Cleared | 11/9/2021 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 11/24/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/24/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | CELINA MORENO |
Contact Information
| Contractor | Moreno Chris; Lic. No.: 973501-B | 1158 W 126TH STREET LOS ANGELES, CA 90044 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2022 | Approved | JOAQUIN GREENOUGH |
| Sewer | 4/8/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 4/8/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 4/8/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 4/11/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/24/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 5/27/2022 | Partial Approval | RYAN SALAZAR |
| Pre-Inspection | 5/27/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Drywall Nailing | 6/21/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/24/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/14/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/14/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 10/19/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 10/19/2022 | Approved | ALEJANDRO DE ARTOLA |