818 3/4 E 87TH PL 90002

Certificate Information: 818 3/4 E 87TH PL 90002

Application / Permit
21010-10000-04724
Plan Check / Job No.
B21LA16911
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) 1 OF 2
Permit Issued
Issued on 9/11/2023
Issuing Office
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 KEVIN MORALES
Corrections Issued 10/20/2021 KEVIN MORALES
Quality Review Completed 10/25/2021 EUGENE BARBEAU
Building Plans Picked Up 10/28/2021 APPLICANT
Plan Check Approved 9/11/2023 KEVIN MORALES
Issued 9/11/2023 APPLICANT
CofO in Progress 12/23/2025 JOHN QUINTANILLA
Permit Finaled 12/23/2025 DEROLD HAUFF
CofO Issued 12/23/2025 DEROLD HAUFF
Permit Finaled 12/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/10/2021 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 11/16/2021 KHOUNG LE
Sewer availability Cleared 11/16/2021 KHOUNG LE
Low Impact Development Cleared 5/18/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/19/2022 KHOUNG LE

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/28/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 11/28/2023 Approved MICHAEL LEWIS
Underground Mechanical 11/28/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 1/8/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 1/8/2024 Conditional Approval MICHAEL LEWIS
PLUMBING-Rough 1/8/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/23/2024 Approved MICHAEL LEWIS
Green Building Rough 1/23/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 1/23/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 1/23/2024 Approved MICHAEL LEWIS
Insulation 2/8/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 2/8/2024 Approved JOSE MACIAS
Drywall Nailing 2/26/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/26/2024 Approved MICHAEL LEWIS
Sewer 3/6/2024 Approved MICHAEL LEWIS
Underground Mechanical 3/6/2024 Partial Approval MICHAEL LEWIS
Final 8/26/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 8/26/2025 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 8/26/2025 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 8/26/2025 Approved SALVADOR MARTINEZ
Final 11/25/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 11/25/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 11/25/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 12/2/2025 OK to Issue CofO JOHN QUINTANILLA
Service/Power Release 12/2/2025 Approved JOHN QUINTANILLA