2228 W OAK GLEN PL 90039
Certificate Information: 2228 W OAK GLEN PL 90039
- Application / Permit
- 21010-10000-04703
- Plan Check / Job No.
- B21LA16834
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | DANIEL YIP |
| Corrections Issued | 10/27/2021 | DANIEL YIP |
| Quality Review Completed | 11/5/2021 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 3/18/2022 | DANIEL YIP |
| Issued | 5/3/2022 | APPLICANT |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| CofO in Progress | 3/28/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 4/3/2025 | DEROLD HAUFF |
| CofO Issued | 4/3/2025 | DEROLD HAUFF |
| Permit Finaled | 4/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2021 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 1/3/2022 | TREVOR QUAN |
| Street Frontage | Cleared | 1/14/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 2/23/2022 | KHAING AYE |
| Hydrant and Access approval | Cleared | 3/4/2022 | DWAYNE LAURENT |
| GPI Written Notices | Cleared | 3/17/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 3/17/2022 | DANIEL YIP |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: C43117 | 9234 STAMPS AVE DOWNEY, CA 90240 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/9/2022 | Partial Inspection | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 5/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 5/17/2022 | Partial Inspection | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 5/23/2022 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/31/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/16/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 7/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/4/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 8/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 8/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 8/4/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 9/9/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 9/9/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/9/2022 | Partial Approval | THOMAS LOGRASSO |
| MERV13>=Rough | 9/9/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/9/2022 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 9/9/2022 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 9/22/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/3/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/3/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 10/3/2022 | Approved | THOMAS LOGRASSO |
| Deck | 10/20/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/15/2022 | Approved | THOMAS LOGRASSO |
| Green Building Final | 12/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 12/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 12/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 12/15/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| ELECTRICAL-Final | 2/20/2025 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 2/20/2025 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Final | 2/20/2025 | Corrections Issued | CRAIG DAVIS |
| Pre-Inspection | 2/20/2025 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 3/5/2025 | No Access for Inspection | WILLIAM SIERRA |
| Final | 3/20/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 3/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 3/20/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 3/20/2025 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 3/20/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 3/20/2025 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 3/25/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 3/25/2025 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/25/2025 | Approved | HAMIK HARTOUNIAN |