Excavation/Setback/Form/Re-Bar
|
5/10/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
5/10/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Pre-Inspection
|
5/10/2023
|
Corrections Issued
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
5/22/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
9/18/2023
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2023
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Footing/Foundation/Slab
|
9/22/2023
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Deputy Reinf. Concrete
|
9/25/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
10/2/2023
|
Corrections Issued
|
JEFFREY FULTON
|
|
Deputy Steel/Welding
|
10/6/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
10/10/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
10/10/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wall Anchors
|
10/10/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
10/11/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
10/11/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
10/13/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
10/16/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2023
|
Corrections Issued
|
JEFFREY FULTON
|
|
Green Building Rough
|
11/8/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
11/8/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
11/8/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/9/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
11/13/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
11/14/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/14/2023
|
Corrections Issued
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
11/14/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
11/14/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
11/14/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
11/14/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
11/21/2023
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/22/2023
|
Partial Approval
|
CAMERON CHABAN
|
|
Green Building Rough
|
11/22/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Verify Sprinkler Sign Off
|
11/22/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Wood Frame
|
11/22/2023
|
Not Ready for Inspection
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
12/1/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Masonry
|
12/1/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Green Building Rough
|
12/4/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
12/4/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
12/4/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
12/4/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
12/5/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
12/6/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
12/6/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
12/7/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Green Building Rough
|
12/18/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
12/18/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
12/18/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
12/21/2023
|
Conditional Approval
|
JEFFREY FULTON
|
|
Green Building Rough
|
12/21/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
12/21/2023
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
12/21/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Deputy Wood Construction
|
12/22/2023
|
Conditional Approval
|
CAMERON CHABAN
|
|
Interior/Exterior Lathing
|
12/27/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
12/29/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
1/5/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
1/5/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
1/5/2024
|
Corrections Issued
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/9/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/9/2024
|
Partial Inspection
|
MELVIN GIRTON
|
|
Green Building Rough
|
1/9/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
1/9/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
1/9/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/17/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
1/17/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
1/17/2024
|
Partial Inspection
|
MELVIN GIRTON
|
|
Verify Sprinkler Sign Off
|
1/17/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
1/17/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
1/24/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
1/24/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
1/24/2024
|
Corrections Issued
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/26/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
1/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
2/1/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
T-Bar Ceiling
|
2/29/2024
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Final
|
4/15/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
4/15/2024
|
Approved
|
GREGORY POMISH
|
|
Green Building Final
|
4/15/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
4/15/2024
|
Approved
|
GREGORY POMISH
|
|
SGSOV-Seismic Gas S/O Valve
|
4/15/2024
|
SGSOV Approved
|
GREGORY POMISH
|
|
Smoke Detectors
|
4/15/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
4/15/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
4/15/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Final
|
5/14/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Final
|
5/14/2024
|
Approved
|
GREGORY POMISH
|
|
Smoke Detectors
|
5/14/2024
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
5/14/2024
|
Approved
|
GREGORY POMISH
|
|
Wood Frame
|
5/14/2024
|
Approved
|
GREGORY POMISH
|
|
Final
|
5/21/2024
|
OK to Issue CofO
|
GREGORY POMISH
|
|
Smoke Detectors
|
5/21/2024
|
Approved
|
GREGORY POMISH
|