6319 W 84TH PL 90045

Certificate Information: 6319 W 84TH PL 90045

Application / Permit
21010-10000-04650
Plan Check / Job No.
B21LA16710
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Ground floor and second floor addition to an (E) detached garage. Conversion of second floor into an ADU per ordinance 186,481 and addition to (E) agrage for new workshop and a half bath.
Permit Issued
Issued on 3/11/2022
Issuing Office
Current Status
CofO Issued on 3/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 HELEN NGUYEN
Corrections Issued 9/13/2021 HELEN NGUYEN
Applicant returned to address corrections 2/18/2022 HELEN NGUYEN
Plan Check Approved 3/11/2022 FARSHAD ALIMOHAMADI
Issued 3/11/2022 APPLICANT
CofO in Progress 3/10/2023 HERBERT GIRON
Permit Finaled 3/15/2023 DANIEL ORRANTE
CofO Issued 3/15/2023 DANIEL ORRANTE
Permit Finaled 3/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/15/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/17/2022 JOSE HERNANDEZ
Sewer availability Cleared 1/17/2022 JOSE HERNANDEZ
Construction within easement Cleared 1/24/2022 WALTER RAMIREZ
Low Impact Development Cleared 1/31/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 2/1/2022 ERIK BEASLEY
Specific Plan Cleared 2/10/2022 PEDRO AYALA

Contact Information

Contractor Sharp Builders Construction Inc; Lic. No.: 884884-B       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342
Engineer Gosen,, James W; Lic. No.: NA43590       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/25/2022 Approved BOBBY KEY
Footing/Foundation/Slab 3/25/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 4/8/2022 Approved BOBBY KEY
Underground Mechanical 4/8/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 6/24/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 6/24/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/24/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 6/28/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 6/28/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved JESUS RODRIGUEZ
Green Building Rough 6/28/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 6/28/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/28/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/26/2022 Approved BOBBY KEY
Green Building Rough 7/26/2022 Not Ready for Inspection BOBBY KEY
Insulation 7/26/2022 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 7/26/2022 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 8/2/2022 Partial Approval HERBERT GIRON
Green Building Rough 8/2/2022 Approved HERBERT GIRON
Insulation 8/2/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/2/2022 Partial Approval HERBERT GIRON
Drywall Nailing 8/12/2022 Approved HERBERT GIRON
Shower Pan 8/12/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/19/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/19/2023 Approved HERBERT GIRON
ELECTRICAL-Final 1/19/2023 Corrections Issued HERBERT GIRON
Final 1/19/2023 Corrections Issued HERBERT GIRON
Green Building Final 1/19/2023 Corrections Issued HERBERT GIRON
HVAC-Final 1/19/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 1/19/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/19/2023 Approved HERBERT GIRON
ELECTRICAL-Final 2/28/2023 Corrections Issued HERBERT GIRON
Final 2/28/2023 Corrections Issued HERBERT GIRON
Green Building Final 2/28/2023 Approved HERBERT GIRON
HVAC-Final 2/28/2023 Approved HERBERT GIRON
PLUMBING-Final 2/28/2023 Approved HERBERT GIRON
Service/Power Release 2/28/2023 Not Ready for Inspection HERBERT GIRON
Service/Power Release 3/2/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 3/3/2023 Approved HERBERT GIRON
Service/Power Release 3/3/2023 Not Ready for Inspection HERBERT GIRON
Final 3/9/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 3/9/2023 Approved HERBERT GIRON