12606 W ADMIRAL AVE 90066

Certificate Information: 12606 W ADMIRAL AVE 90066

Application / Permit
21010-10000-04615
Plan Check / Job No.
B21LA16621
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 2-CAR GARAGE AND ROOF DECK.
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 CARLOS MONTES
Corrections Issued 9/30/2021 CARLOS MONTES
Quality Review Completed 10/4/2021 KEN GILL
Applicant returned to address corrections 3/1/2022 CARLOS MONTES
Plan Check Approved 4/5/2022 CARLOS MONTES
Building Plans Picked Up 5/3/2022 APPLICANT
Issued 5/5/2022 APPLICANT
CofO in Progress 8/2/2023 HERBERT GIRON
Permit Finaled 8/8/2023 DANIEL ORRANTE
CofO Issued 8/8/2023 DANIEL ORRANTE
Permit Finaled 8/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 10/11/2021 KEVIN ARUCAN
Eng Process Fee Ord 176,300 Cleared 10/13/2021 DINAH GARIN
Sewer availability Cleared 10/13/2021 DINAH GARIN
Hydrant and Access approval Cleared 2/23/2022 GREGORY HOERNER
Low Impact Development Cleared 3/9/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/10/2022 DINAH GARIN
Hold Cleared 5/12/2022 JASON SHEETS

Contact Information

Contractor Blue Phoenix Builders Inc; Lic. No.: 1066549-B 4474 W ADAMS BLVD #205      LOS ANGELES, CA 90016
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/25/2022 Corrections Issued RICHARD STEINBACH
Underground Mechanical 5/27/2022 Approved CLAYTON GRAHAM
Footing/Foundation/Slab 6/2/2022 Not Ready for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 9/12/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 9/14/2022 Partial Approval HERBERT GIRON
Pre-Inspection 9/14/2022 Not Ready for Inspection HERBERT GIRON
Deputy Reinf. Concrete 9/15/2022 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 10/6/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Corrections Issued HERBERT GIRON
Deputy Wood Construction 10/18/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval HERBERT GIRON
Deputy Wood Construction 12/21/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval EVAN COOPER
Deputy Steel/Welding 12/28/2022 Conditional Approval RICHARD STEINBACH
HVAC-Rough 1/31/2023 Corrections Issued HERBERT GIRON
Gas Test 2/1/2023 Corrections Issued HERBERT GIRON
PLUMBING-Rough 2/1/2023 Corrections Issued HERBERT GIRON
Sewer 2/1/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 2/7/2023 Not Ready for Inspection HERBERT GIRON
Gas Test 2/7/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 2/7/2023 Approved HERBERT GIRON
Sewer 2/7/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 2/10/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/22/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 2/22/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 3/7/2023 Approved HERBERT GIRON
Green Building Rough 3/7/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/7/2023 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 3/9/2023 Conditional Approval HERBERT GIRON
Final 3/9/2023 Corrections Issued HERBERT GIRON
Verify Sprinkler Sign Off 3/9/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/17/2023 Approved HERBERT GIRON
Insulation 3/17/2023 Corrections Issued HERBERT GIRON
Insulation 3/21/2023 Approved HERBERT GIRON
Shower Pan 3/21/2023 Approved HERBERT GIRON
Drywall Nailing 3/28/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 4/10/2023 Approved JESUS PINEDA
ELECTRICAL-Final 7/7/2023 Corrections Issued HERBERT GIRON
Gas Test 7/7/2023 Approved HERBERT GIRON
PLUMBING-Final 7/7/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 7/7/2023 Approved HERBERT GIRON
ELECTRICAL-Final 7/13/2023 Approved HERBERT GIRON
HVAC-Final 7/13/2023 Corrections Issued HERBERT GIRON
HVAC-Final 7/19/2023 Corrections Issued HERBERT GIRON
Final 7/25/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 7/25/2023 Approved HERBERT GIRON
Green Building Final 7/25/2023 Approved HERBERT GIRON
HVAC-Final 7/25/2023 Approved HERBERT GIRON
Service/Power Release 7/25/2023 Conditional Approval HERBERT GIRON
Final 7/28/2023 Corrections Issued HERBERT GIRON
Final 8/2/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 8/2/2023 Approved HERBERT GIRON