12606 W ADMIRAL AVE 90066
Certificate Information: 12606 W ADMIRAL AVE 90066
- Application / Permit
- 21010-10000-04615
- Plan Check / Job No.
- B21LA16621
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 2-CAR GARAGE AND ROOF DECK.
- Permit Issued
- Issued on 5/5/2022
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | CARLOS MONTES |
| Corrections Issued | 9/30/2021 | CARLOS MONTES |
| Quality Review Completed | 10/4/2021 | KEN GILL |
| Applicant returned to address corrections | 3/1/2022 | CARLOS MONTES |
| Plan Check Approved | 4/5/2022 | CARLOS MONTES |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Issued | 5/5/2022 | APPLICANT |
| CofO in Progress | 8/2/2023 | HERBERT GIRON |
| Permit Finaled | 8/8/2023 | DANIEL ORRANTE |
| CofO Issued | 8/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/11/2021 | KEVIN ARUCAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/13/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 2/23/2022 | GREGORY HOERNER |
| Low Impact Development | Cleared | 3/9/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/10/2022 | DINAH GARIN |
| Hold | Cleared | 5/12/2022 | JASON SHEETS |
Contact Information
| Contractor | Blue Phoenix Builders Inc; Lic. No.: 1066549-B | 4474 W ADAMS BLVD #205 LOS ANGELES, CA 90016 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/25/2022 | Corrections Issued | RICHARD STEINBACH |
| Underground Mechanical | 5/27/2022 | Approved | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 6/2/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/12/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | HERBERT GIRON |
| Pre-Inspection | 9/14/2022 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Reinf. Concrete | 9/15/2022 | Conditional Approval | HERBERT GIRON |
| Deputy Steel/Welding | 10/6/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Corrections Issued | HERBERT GIRON |
| Deputy Wood Construction | 10/18/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 12/21/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 12/28/2022 | Conditional Approval | RICHARD STEINBACH |
| HVAC-Rough | 1/31/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 2/1/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/1/2023 | Corrections Issued | HERBERT GIRON |
| Sewer | 2/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 2/7/2023 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 2/7/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 2/7/2023 | Approved | HERBERT GIRON |
| Sewer | 2/7/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 2/10/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 2/22/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 2/22/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 3/7/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 3/7/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 3/7/2023 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/9/2023 | Conditional Approval | HERBERT GIRON |
| Final | 3/9/2023 | Corrections Issued | HERBERT GIRON |
| Verify Sprinkler Sign Off | 3/9/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | HERBERT GIRON |
| Insulation | 3/17/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 3/21/2023 | Approved | HERBERT GIRON |
| Shower Pan | 3/21/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/28/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/10/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 7/7/2023 | Corrections Issued | HERBERT GIRON |
| Gas Test | 7/7/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/7/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 7/7/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/13/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 7/13/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 7/19/2023 | Corrections Issued | HERBERT GIRON |
| Final | 7/25/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 7/25/2023 | Approved | HERBERT GIRON |
| Green Building Final | 7/25/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 7/25/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 7/25/2023 | Conditional Approval | HERBERT GIRON |
| Final | 7/28/2023 | Corrections Issued | HERBERT GIRON |
| Final | 8/2/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 8/2/2023 | Approved | HERBERT GIRON |