940 S PATTON AVE 90731

Certificate Information: 940 S PATTON AVE 90731

Application / Permit
21010-10000-04600
Plan Check / Job No.
B21LA16549
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
PROPOSED 1-STORY DETACHED GARAGE AT REAR OF LOT.
Permit Issued
Issued on 5/30/2024
Issuing Office
San Pedro
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/10/2021 LAWRENCE QUIRANTE
Corrections Issued 9/13/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 9/17/2021 APPLICANT
Plan Check Approved 7/28/2022 RAHEL BEYENE
Issued 5/30/2024 APPLICANT
CofO in Progress 2/18/2025 JOSEPH MCGARRY
Permit Finaled 2/18/2025 ANSON MAGLASANG
CofO Issued 2/18/2025 ANSON MAGLASANG
Permit Finaled 2/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/14/2022 ERIK BEASLEY
Roof/Waste drainage to street Cleared 4/14/2022 ERIK BEASLEY
Grading Pre-Inspection Cleared 5/30/2024 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/13/2024 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/5/2024 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 11/13/2024 Approved JOSEPH MCGARRY
Wood Frame 11/13/2024 Conditional Approval JOSEPH MCGARRY
Drywall Nailing 12/11/2024 Approved JOSEPH MCGARRY
Green Building Rough 12/11/2024 Approved JOSEPH MCGARRY
Wood Frame 12/11/2024 Approved JOSEPH MCGARRY
Final 1/29/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 1/29/2025 Approved BEN MOLSTAD
Green Building Final 1/29/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 1/29/2025 Approved BEN MOLSTAD
Final 1/31/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Approved BEN MOLSTAD
Final 2/7/2025 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved JOSEPH MCGARRY