1743 1/2 W 37TH DR 90018
Certificate Information: 1743 1/2 W 37TH DR 90018
- Application / Permit
- 21010-10000-04561
- Plan Check / Job No.
- B21LA16455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 11/15/2022
- Issuing Office
- Current Status
- CofO Corrected on 5/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | CARLOS MONTES |
| Corrections Issued | 10/20/2021 | CARLOS MONTES |
| Quality Review Completed | 10/25/2021 | WING SUEN |
| Applicant returned to address corrections | 12/30/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 5/27/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 9/19/2022 | CARLOS MONTES |
| Plan Check Approved | 11/15/2022 | CARLOS MONTES |
| Issued | 11/15/2022 | APPLICANT |
| CofO in Progress | 11/12/2025 | SABAS ALONSO |
| CofO Issued-Status Void | 11/14/2025 | DEROLD HAUFF |
| Permit Finaled-Status Void | 11/14/2025 | DEROLD HAUFF |
| Re-Activate Permit | 5/6/2026 | DEROLD HAUFF |
| Permit Finaled | 5/6/2026 | DEROLD HAUFF |
| CofO Corrected | 5/6/2026 | DEROLD HAUFF |
| Permit Finaled | 5/6/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | CHRISTOPHER ROCHA |
| Community Plan Implem. Overlay | Cleared | 12/16/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/16/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2021 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 1/11/2022 | RICARDO BOHORQUEZ |
| Community Plan Implem. Overlay | Cleared | 1/26/2022 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 3/15/2022 | TINA MIRANDA |
| Low Impact Development | Cleared | 3/24/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | CHRISTOPHER ROCHA |
| Community Plan Implem. Overlay | Cleared | 4/5/2022 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/23/2022 | Partial Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Not Ready | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/2/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/2/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Partial Approval | STUART CHAPMAN |
| Gas Test | 9/11/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 9/11/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/11/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/11/2023 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 9/25/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/25/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 10/18/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 10/19/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/17/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/17/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 11/17/2023 | Approved | SABAS ALONSO |
| Shower Pan | 11/17/2023 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 11/17/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/4/2023 | Approved | SABAS ALONSO |
| Shower Pan | 12/4/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 2/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| Gas Test | 2/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 3/11/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/11/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 3/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 3/11/2024 | Approved | SABAS ALONSO |
| Final | 8/6/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/6/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 8/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 10/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 10/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/6/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 11/6/2025 | Approved | SABAS ALONSO |