9704 S KALMIA ST 2100-2306 90002
Certificate Information: 9704 S KALMIA ST 2100-2306 90002
- Application / Permit
- 21010-10000-04545
- Plan Check / Job No.
- B21LA16181
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 21 UNITS TYPE VA APARTMENT PER JORDAN DOWNS SPECIFIC PLAN.
- Permit Issued
- Issued on 4/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Issued | 4/12/2022 | APPLICANT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| TCO Issued (Expire Date: 05-19-2025) | 11/20/2024 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 11-15-2025) | 5/19/2025 | RAFAEL ESPINOZA |
| CofO in Progress | 5/20/2025 | JAMES POWERS |
| Permit Finaled | 5/27/2025 | ERNESTO CORRAL |
| CofO Issued | 5/27/2025 | ERNESTO CORRAL |
| Permit Finaled | 5/27/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | CELINA MORENO |
| City owned building/parcel | Cleared | 1/4/2022 | KEVIN MORALES |
| Address approval | Cleared | 2/15/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/24/2022 | KURT CORRAL |
| Public Housing | Cleared | 3/8/2022 | SUNYOUNG KIM |
| Trees in Parkway | Cleared | 3/16/2022 | JOEL HERNANDEZ |
| Low Impact Development | Cleared | 3/18/2022 | MARTIN FRAGOSO |
| Green Code | Cleared | 3/22/2022 | KEVIN MORALES |
| Frnt yard landscape/Water mgmt | Cleared | 3/24/2022 | JASON CHAN |
| Miscellaneous | Cleared | 3/24/2022 | JASON CHAN |
| Miscellaneous | Cleared | 3/24/2022 | JASON CHAN |
| Miscellaneous | Cleared | 3/24/2022 | JASON CHAN |
| Opn space landscape/Water mgmt | Cleared | 3/24/2022 | JASON CHAN |
| Site Plan review | Cleared | 3/24/2022 | JASON CHAN |
| Tract Map conditions | Cleared | 3/24/2022 | JASON CHAN |
| Tract Map conditions | Cleared | 3/24/2022 | JASON CHAN |
| ZA Case | Cleared | 3/24/2022 | JASON CHAN |
| ZA Case | Cleared | 3/24/2022 | JASON CHAN |
| ZA Case | Cleared | 3/24/2022 | JASON CHAN |
| Building over 36-ft | Cleared | 3/29/2022 | CALOSHA APPROVED |
| Highway dedication | Cleared | 3/31/2022 | JEANETTE VONG |
| Permit | Cleared | 3/31/2022 | MATIAS FARFAN |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | MATIAS FARFAN |
| Fire Marshal Fire Life Safety | Cleared | 4/1/2022 | OSCAR SALGADO JR |
| Sewer availability | Cleared | 4/1/2022 | MATIAS FARFAN |
| DAS Clearance | Cleared | 4/12/2022 | KEVIN MORALES |
| Miscellaneous | Cleared | 4/12/2022 | CONNIE CHAUV |
| Specific Plan | Cleared | 4/12/2022 | CONNIE CHAUV |
Contact Information
| Contractor | Portrait Construction Inc; Lic. No.: 977636-B | 265 N JOY STREET #200 CORONA, CA 92879 |
| Engineer | Aden,, Mark; Lic. No.: S4779 | , |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 10/14/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 10/14/2022 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Concrete | 11/3/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 11/3/2022 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 11/14/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 11/28/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/6/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 12/16/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 1/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 1/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Insulation | 1/24/2023 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 2/3/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 2/15/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 2/15/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/15/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 2/15/2023 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 2/28/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 3/6/2023 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 3/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | GREGORY POMISH |
| Insulation | 3/10/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 3/24/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 3/24/2023 | Approved | JAMES POWERS |
| Insulation | 4/5/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 5/15/2023 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 5/24/2023 | Partial Approval | JAMES POWERS |
| Insulation | 7/6/2023 | Partial Approval | JAMES POWERS |
| Insulation | 7/12/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/19/2023 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 7/24/2023 | Partial Approval | JAMES POWERS |
| Insulation | 8/3/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/30/2023 | Partial Approval | JAMES POWERS |
| Insulation | 1/17/2024 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 4/8/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 4/19/2024 | Approved | JAMES POWERS |
| Special/Order Compliance | 10/7/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 11/7/2024 | Approved | JAMES POWERS |
| Final | 11/7/2024 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 11/7/2024 | Approved | JAMES POWERS |
| Green Building Final | 11/7/2024 | Approved | JAMES POWERS |
| Reinforced Concrete Frame | 11/7/2024 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 11/7/2024 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | JAMES POWERS |
| Wood Frame | 11/7/2024 | Approved | JAMES POWERS |
| Final | 11/20/2024 | OK for TCO | JAMES POWERS |
| Special/Order Compliance | 4/22/2025 | Not Ready for Inspection | JAMES POWERS |
| Final | 5/20/2025 | OK to Issue CofO | JAMES POWERS |