2275 S PARNELL AVE 90064
Certificate Information: 2275 S PARNELL AVE 90064
- Application / Permit
- 21010-10000-04499
- Plan Check / Job No.
- B21LA16305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT EXISTING GARAGE TO 1 STORY ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- Issued on 5/30/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 9/2/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/16/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 9/22/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 10/4/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 10/5/2021 | CRYSTEL MAALOUF |
| Issued | 10/8/2021 | APPLICANT |
| Refund in Progress | 1/26/2022 | TERENCE SHIA |
| Refund Denied | 5/30/2022 | CHRISTINE ISIDRO |
| Issued | 5/30/2022 | CHRISTINE ISIDRO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2021 | CATHERINE ADROVER |
| Specific Plan | Cleared | 9/27/2021 | VALERIA CEJA |
| Address approval | Cleared | 9/29/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 9/29/2021 | SAUL GARCIA |
Contact Information
| Architect | Chang,, Eric Cheng-Che; Lic. No.: NA25031 | , |
| Contractor | Nucon Group Inc; Lic. No.: 748689-B | 10336 MONTE MAR DRIVE LOS ANGELES, CA 90064 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2021 | Partial Inspection | BRENDAN LOONEY |
| Sewer | 10/18/2021 | Corrections Issued | BRENDAN LOONEY |
| Sewer | 10/20/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/21/2021 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/9/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/9/2021 | Corrections Issued | BRENDAN LOONEY |
| FLOOD-Proofing Certificate | 11/9/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 11/9/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 11/9/2021 | Approved | BRENDAN LOONEY |
| METHANE-Rough | 11/9/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 11/9/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/18/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/18/2021 | Approved | BRENDAN LOONEY |
| FLOOD-Proofing Certificate | 11/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |