3765 3/4 S DELMAS TER 90034

Certificate Information: 3765 3/4 S DELMAS TER 90034

Application / Permit
21010-10000-04488
Plan Check / Job No.
B21LA16214
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 4/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2021 APPLICANT
Assigned to Plan Check Engineer 10/4/2021 KHEDER ALRAZAA
Corrections Issued 10/7/2021 KHEDER ALRAZAA
Quality Review Completed 10/14/2021 ALLEN MANALANSAN
Building Plans Picked Up 10/19/2021 APPLICANT
Applicant returned to address corrections 9/15/2022 KHEDER ALRAZAA
Plan Check Approved 10/25/2022 KHEDER ALRAZAA
Issued 4/13/2023 APPLICANT
CofO in Progress 4/17/2024 OGANES TARAKHCHYAN
Permit Finaled 4/30/2024 DANIEL ORRANTE
CofO Issued 4/30/2024 DANIEL ORRANTE
Permit Finaled 4/30/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/22/2022 JEANETTE VONG
Permit Cleared 1/22/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/28/2022 JEANETTE VONG
Sewer availability Cleared 1/28/2022 JEANETTE VONG
ZA Case Cleared 2/23/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 3/29/2022 JOHN CONNEALLY
Trees in Parkway Cleared 4/21/2022 ADALBERTO VERA
Construction within easement Cleared 4/29/2022 RIDWAN HARDY
Miscellaneous Cleared 6/9/2022 SAUL GARCIA
Low Impact Development Cleared 6/16/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 6/17/2022 SAUL GARCIA
Grading Pre-Inspection Cleared 10/25/2022 KHEDER ALRAZAA

Contact Information

Contractor Truebuilt Construction Inc; Lic. No.: 1052087-B 950 E KATELLA AVE STE 5      ORANGE, CA 92867
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/18/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 5/18/2023 Not Ready for Inspection CLAYTON GRAHAM
Underground Mechanical 5/30/2023 Partial Approval CLAYTON GRAHAM
Footing/Foundation/Slab 6/2/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 10/11/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/11/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 10/12/2023 Not Ready for Inspection CLAYTON GRAHAM
Verify Sprinkler Sign Off 10/12/2023 Approved CLAYTON GRAHAM
HVAC-Rough 10/13/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 10/20/2023 Approved CLAYTON GRAHAM
HVAC-Rough 10/20/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 10/20/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 10/23/2023 Approved CLAYTON GRAHAM
Special/Order Compliance 10/23/2023 Corrections Issued CLAYTON GRAHAM
Insulation 11/2/2023 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 11/6/2023 Corrections Issued OGANES TARAKHCHYAN
Insulation 11/7/2023 Approved OGANES TARAKHCHYAN
Special/Order Compliance 11/13/2023 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 11/14/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/30/2023 Approved JESUS PINEDA
Shower Pan 11/30/2023 Approved JESUS PINEDA
Underground Mechanical 1/10/2024 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 1/12/2024 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 1/22/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 1/29/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 3/7/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 3/13/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 3/26/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 3/26/2024 Approved OGANES TARAKHCHYAN
Final 4/9/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 4/9/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/9/2024 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 4/9/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 4/9/2024 Approved OGANES TARAKHCHYAN
Final 4/16/2024 OK to Issue CofO OGANES TARAKHCHYAN