2826 3/4 W LEEWARD AVE 90005
Certificate Information: 2826 3/4 W LEEWARD AVE 90005
- Application / Permit
- 21010-10000-04475
- Plan Check / Job No.
- B21LA16178
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. NEW 2-STORY ACCESSORY BUILDING. 4 CAR GARAGE AT 1ST FLOOR & ACCESSORY DWELLING UNIT AT 2ND FLOOR.
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | PRANITA SHAH |
| Corrections Issued | 10/19/2021 | PRANITA SHAH |
| Quality Review Completed | 11/4/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 7/14/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 8/9/2022 | PRANITA SHAH |
| Plan Check Approved | 8/23/2022 | PRANITA SHAH |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 5/3/2024 | NICK DANERI |
| Permit Finaled | 5/6/2024 | ERNESTO CORRAL |
| CofO Issued | 5/6/2024 | ERNESTO CORRAL |
| Permit Finaled | 5/6/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | KHOUNG LE |
| Permit | Cleared | 11/22/2021 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | KHOUNG LE |
| Hydrant and Access approval | Cleared | 3/7/2022 | LARRY REDDEN |
| Low Impact Development | Cleared | 4/15/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | JEANIE LAM |
| Sewer availability | Cleared | 4/20/2022 | JEANIE LAM |
Contact Information
| Architect | Park,, Yong Keun; Lic. No.: NA24806 | , |
| Contractor | C & Construction; Lic. No.: 1048015-B | , |
| Contractor | Tj Construction & Remodeling Inc; Lic. No.: 1048015-B | , |
| Engineer | Lee,, Sang Youck; Lic. No.: NA3821 | , |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/3/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 11/3/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 11/3/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 11/9/2022 | Corrections Issued | NICK DANERI |
| METHANE-Barrier | 11/9/2022 | Not Ready for Inspection | NICK DANERI |
| METHANE-Subgrade | 11/9/2022 | Not Ready for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 11/28/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 11/28/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 11/28/2022 | Approved | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/9/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 2/14/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 2/21/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/21/2023 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 5/16/2023 | Approved | STUART CHAPMAN |
| Pre-Inspection | 5/24/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Wood Frame | 5/24/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Pre-Inspection | 5/30/2023 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 5/30/2023 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 6/1/2023 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 6/6/2023 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 6/7/2023 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Partial Approval | GREGORY POMISH |
| Wood Frame | 8/2/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Wood Construction | 8/7/2023 | Conditional Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 8/18/2023 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 8/18/2023 | Not Ready for Inspection | GREGORY POMISH |
| Drywall Nailing | 8/23/2023 | Partial Approval | LARRY ARNICK |
| Green Building Rough | 8/23/2023 | Not Ready for Inspection | LARRY ARNICK |
| Drywall Nailing | 8/31/2023 | Approved | LARRY ARNICK |
| Green Building Rough | 8/31/2023 | Approved | LARRY ARNICK |
| BUILDING-Rough-Frame | 4/4/2024 | Approved | NICK DANERI |
| Final | 4/4/2024 | Corrections Issued | NICK DANERI |
| Green Building Final | 4/4/2024 | Approved | NICK DANERI |
| METHANE-Final | 4/4/2024 | Approved | NICK DANERI |
| METHANE-Rough | 4/4/2024 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | NICK DANERI |
| Service/Power Release | 4/4/2024 | Not Ready for Inspection | NICK DANERI |
| Smoke Detectors | 4/4/2024 | Approved | NICK DANERI |
| Structural Steel Frame | 4/4/2024 | Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 4/4/2024 | Approved | NICK DANERI |
| Final | 4/24/2024 | Partial Inspection | EDWIN GREGORYONA |
| Service/Power Release | 4/24/2024 | Approved | EDWIN GREGORYONA |
| Verify Rec and Parks Fee Memo | 4/24/2024 | Approved | EDWIN GREGORYONA |
| Final | 5/3/2024 | OK to Issue CofO | NICK DANERI |