7837 N STANSBURY AVE 91402
Certificate Information: 7837 N STANSBURY AVE 91402
- Application / Permit
- 21010-10000-04456
- Plan Check / Job No.
- B21LA16149
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY A.D.U. [47 X 25] AT REAR OF LOT PER ORDINANCE [3 BEDROOMS, 2 BATHROOMS]
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 6/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/1/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 2/10/2022 | JESSE JIMENEZ |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | DAVID MATSON |
| Permit Finaled | 6/15/2023 | MICHAEL SMITH |
| Permit Finaled | 6/15/2023 | MICHAEL SMITH |
| CofO Issued | 6/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/30/2021 | LEE GUILBEAUX |
| Address approval | Cleared | 12/6/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/19/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 1/19/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/19/2022 | LEE GUILBEAUX |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/18/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 4/18/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 4/18/2022 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/22/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/29/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 6/29/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 6/29/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 6/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 8/4/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 8/4/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 8/4/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | GREGG CUMMINGS |
| Insulation | 9/6/2022 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 10/11/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | WILLIAM WREN |
| Shower Pan | 10/25/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/27/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/27/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/27/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/27/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/27/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/27/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/27/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/25/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/25/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 6/1/2023 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 6/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 6/8/2023 | Approved | DAVID MATSON |
| Final | 6/8/2023 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 6/8/2023 | Approved | DAVID MATSON |