Deputy Methane Barrier
|
4/3/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
4/17/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
4/20/2023
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
5/12/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/15/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
5/15/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Barrier
|
5/15/2023
|
Approved
|
EDWIN GREGORYONA
|
|
METHANE-Subgrade
|
5/15/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
5/18/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
5/19/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
5/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
5/23/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/2/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/2/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/5/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
6/6/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
6/7/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Methane Barrier
|
6/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
6/9/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
METHANE-Rough
|
6/9/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
6/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
6/9/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/12/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
6/13/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
6/13/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
6/13/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
6/13/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
6/13/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
6/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
6/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/16/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/23/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
6/23/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
6/23/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
6/23/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
6/27/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
6/27/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
6/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Shotcrete
|
6/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
6/30/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
6/30/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
6/30/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
7/7/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Masonry
|
7/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
7/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
7/11/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
7/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
7/11/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
7/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
7/18/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
7/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
7/18/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
7/20/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
7/21/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/21/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/21/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
7/24/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
7/24/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
7/27/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
7/27/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
7/27/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
7/28/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
8/2/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
8/9/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
8/10/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
8/10/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
8/10/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Other (see comments)
|
8/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
8/17/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
8/17/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
8/17/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
8/29/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
8/30/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
8/31/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
9/1/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/1/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/1/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
9/1/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
9/1/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/6/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
9/11/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
9/13/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
9/13/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
9/13/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
9/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
9/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/18/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Reinforced Concrete Frame
|
9/18/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/18/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
9/19/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
9/19/2023
|
Corrections Issued
|
LARRY ARNICK
|
|
Deputy Shotcrete
|
9/19/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wall Anchors
|
9/19/2023
|
Corrections Issued
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
9/20/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
9/20/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
9/20/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
9/21/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
9/21/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
9/21/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/21/2023
|
Off-Hour Fees Due
|
|
|
Reinforced Concrete Frame
|
9/21/2023
|
Off-Hour Fees Due
|
|
|
Verify Sprinkler Sign Off
|
9/21/2023
|
Off-Hour Fees Due
|
|
|
Deputy Reinf. Concrete
|
9/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
9/22/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/25/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
9/25/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
9/25/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
9/26/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
9/29/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/4/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
10/4/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/4/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/4/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
10/6/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/6/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
10/10/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
10/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/17/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
10/17/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
10/17/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
10/18/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Masonry Wall/Backfill
|
10/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
10/24/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/26/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
10/26/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
10/26/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
10/26/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
10/26/2023
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
10/26/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Wood Frame
|
10/26/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/27/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
11/2/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
11/2/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
11/2/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
11/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
11/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
11/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
11/7/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
11/7/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
11/7/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
11/15/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
11/15/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
11/15/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
11/22/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
11/25/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Reinforced Concrete Frame
|
11/25/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
11/25/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Structural Steel Frame
|
11/28/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
11/29/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
12/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
12/6/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
12/6/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
12/8/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
12/8/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
12/8/2023
|
Approved
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/11/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Pre-Stress Concrete
|
12/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
12/14/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
12/15/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/15/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Pre-Stress Concrete
|
12/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
12/18/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
12/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
1/5/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
1/11/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
1/11/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
1/11/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
1/11/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
1/13/2024
|
Off-Hour Fees Due
|
|
|
Footing/Foundation/Slab
|
1/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
1/22/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
1/22/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
1/22/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
1/22/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
1/22/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
2/15/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
2/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
2/15/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
2/20/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
2/20/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
2/20/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/21/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
2/23/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
2/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
2/23/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
2/29/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Piling/Pier/Caisson
|
2/29/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
2/29/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
2/29/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
3/11/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
3/11/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
3/11/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
3/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
3/19/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
3/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
3/19/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
3/27/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
3/27/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
3/27/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/28/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/5/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
4/5/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/5/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/19/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
4/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/19/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
4/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
4/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/30/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
4/30/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
4/30/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
5/2/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
5/2/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
5/2/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
5/2/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
5/8/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
5/8/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
5/8/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
6/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
6/12/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/12/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Pre-Stress Concrete
|
6/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
6/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
6/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
6/13/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
6/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
6/13/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Footing/Foundation/Slab
|
6/21/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Green Building Rough
|
6/21/2024
|
Approved
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
6/21/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Verify Sprinkler Sign Off
|
6/21/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Piling/Pier/Caisson
|
6/26/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Methane Barrier
|
6/27/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
6/27/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
6/27/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
7/1/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
7/10/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
7/17/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
7/26/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
7/26/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
7/29/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
7/29/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
7/31/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Masonry Wall/Backfill
|
7/31/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
8/6/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
8/7/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
8/13/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
8/14/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
8/14/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
8/29/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
8/29/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
8/29/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
9/3/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Reinforced Masonry Frame
|
9/3/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
9/6/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
9/6/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
9/12/2024
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
9/12/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
9/20/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Light Gage Steel Frame
|
9/20/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Light Gage Steel Frame
|
10/2/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/8/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
10/8/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/10/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
10/10/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
10/11/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
10/15/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/17/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
10/17/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/21/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
10/21/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
10/21/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
10/29/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Steel/Welding
|
10/30/2024
|
Approved
|
CHRISTOPHER BLACKWOOD
|
|
Deputy Steel/Welding
|
11/1/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
11/1/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
11/20/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
11/21/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
11/22/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/4/2024
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
12/5/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
12/9/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
12/18/2024
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
12/19/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
1/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
1/9/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/9/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/13/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/13/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/14/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/17/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/21/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
1/22/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/22/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
1/23/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
1/24/2025
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Drywall Nailing
|
1/27/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
1/28/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/29/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
1/31/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
1/31/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/4/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
2/4/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/5/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/5/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/10/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/10/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/11/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/11/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/12/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/21/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/21/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/25/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
2/25/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
2/28/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
3/4/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/4/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/7/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/11/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/11/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/14/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/18/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/20/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/27/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/27/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
3/28/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
3/28/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
4/1/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/3/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Interior/Exterior Lathing
|
4/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
4/10/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
5/15/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
5/22/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/30/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Light Gage Steel Frame
|
5/30/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
5/30/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/5/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
6/5/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
6/13/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
6/24/2025
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
6/27/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
T-Bar Ceiling
|
7/24/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
8/8/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Final
|
8/25/2025
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
8/25/2025
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Green Building Final
|
8/25/2025
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Reinforced Concrete Frame
|
8/25/2025
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
SGSOV-Seismic Gas S/O Valve
|
8/25/2025
|
SGSOV Not Ready
|
MARTIN TAVITIAN
|
|
Smoke Detectors
|
8/25/2025
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Verify Sprinkler Sign Off
|
8/25/2025
|
Not Ready for Inspection
|
MARTIN TAVITIAN
|
|
Footing/Foundation/Slab
|
9/5/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Final
|
1/22/2026
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
1/22/2026
|
Approved
|
EDWIN GREGORYONA
|
|
Green Building Final
|
1/22/2026
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
1/22/2026
|
Approved
|
EDWIN GREGORYONA
|
|
SGSOV-Seismic Gas S/O Valve
|
1/22/2026
|
SGSOV Approved
|
EDWIN GREGORYONA
|
|
Smoke Detectors
|
1/22/2026
|
Approved
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
1/22/2026
|
Approved
|
EDWIN GREGORYONA
|
|
Final
|
2/3/2026
|
Partial Inspection
|
MARTIN TAVITIAN
|
|
Green Building Final
|
2/3/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Special/Order Compliance
|
2/4/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Pre-Inspection
|
2/12/2026
|
Approved
|
MARTIN TAVITIAN
|
|
Final
|
2/17/2026
|
OK to Issue CofO
|
MARTIN TAVITIAN
|