Special/Order Compliance
|
7/3/2023
|
Corrections Issued
|
AMANUEL BERHE
|
|
Footing/Foundation/Slab
|
10/23/2023
|
Corrections Issued
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
11/7/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
11/13/2023
|
Approved
|
JOEY BUCHANAN
|
|
Pre-Inspection
|
11/13/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
11/14/2023
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
12/4/2023
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Deputy Drilled-In Anchors
|
12/6/2023
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
12/6/2023
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
12/13/2023
|
Approved
|
JOEY BUCHANAN
|
|
Green Building Rough
|
12/29/2023
|
Off-Hour Fees Due
|
|
|
Reinforced Concrete Frame
|
12/29/2023
|
Off-Hour Fees Due
|
|
|
Verify Sprinkler Sign Off
|
12/29/2023
|
Off-Hour Fees Due
|
|
|
Excavation/Setback/Form/Re-Bar
|
1/16/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Reinf. Concrete
|
1/17/2024
|
Approved
|
JOEY BUCHANAN
|
|
Special/Order Compliance
|
2/15/2024
|
Approved
|
JOEY BUCHANAN
|
|
Special/Order Compliance
|
2/21/2024
|
Approved
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
4/26/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
5/2/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/10/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/17/2024
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
5/17/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
6/10/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Pre-Inspection
|
7/31/2024
|
Approved
|
AMANUEL BERHE
|
|
Excavation/Setback/Form/Re-Bar
|
9/13/2024
|
Not Ready for Inspection
|
AMANUEL BERHE
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/23/2024
|
Not Ready for Inspection
|
AMANUEL BERHE
|
|
Excavation/Setback/Form/Re-Bar
|
9/26/2024
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/7/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
10/28/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/9/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
12/10/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Deputy Wood Construction
|
12/20/2024
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/24/2024
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/27/2024
|
Corrections Issued
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/2/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Masonry Wall/Backfill
|
1/9/2025
|
Partial Approval
|
DAVID TSAU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/22/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Masonry Wall/Backfill
|
1/23/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/16/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Insulation
|
5/15/2025
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Insulation
|
6/2/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
6/11/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Pre-Inspection
|
7/25/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Pre-Inspection
|
7/31/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
8/5/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/21/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
8/22/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
8/26/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Interior/Exterior Lathing
|
9/17/2025
|
Corrections Issued
|
RICARDO ROBLES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2025
|
Partial Approval
|
DAVID TSAU
|
|
Pre-Inspection
|
11/24/2025
|
Partial Approval
|
RICARDO ROBLES
|
|
Green Building Rough
|
1/22/2026
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Insulation
|
1/22/2026
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Verify Sprinkler Sign Off
|
1/22/2026
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Wood Frame
|
1/22/2026
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Green Building Rough
|
1/23/2026
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
1/23/2026
|
Not Ready for Inspection
|
RICARDO ROBLES
|
|
Verify Sprinkler Sign Off
|
1/23/2026
|
Partial Approval
|
RICARDO ROBLES
|
|
Wood Frame
|
1/23/2026
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
1/27/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Green Building Rough
|
2/2/2026
|
Partial Approval
|
DAVID TSAU
|
|
Verify Sprinkler Sign Off
|
2/2/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Wood Frame
|
2/2/2026
|
Partial Approval
|
DAVID TSAU
|
|
Drywall Nailing
|
2/3/2026
|
Partial Approval
|
DAVID TSAU
|
|
Pre-Inspection
|
2/3/2026
|
Not Ready for Inspection
|
DAVID TSAU
|
|
Green Building Rough
|
2/5/2026
|
Partial Approval
|
DAVID TSAU
|
|
Pre-Inspection
|
2/5/2026
|
Approved
|
DAVID TSAU
|
|
Verify Sprinkler Sign Off
|
2/5/2026
|
Approved
|
DAVID TSAU
|
|
Green Building Rough
|
2/11/2026
|
Partial Approval
|
DAVID TSAU
|
|
Insulation
|
2/11/2026
|
Partial Approval
|
DAVID TSAU
|
|
Wood Frame
|
2/11/2026
|
Partial Approval
|
DAVID TSAU
|
|
Drywall Nailing
|
2/19/2026
|
Partial Approval
|
DAVID TSAU
|
|
Insulation
|
2/23/2026
|
Partial Approval
|
DAVID TSAU
|
|
Drywall Nailing
|
2/26/2026
|
Partial Approval
|
DAVID TSAU
|
|
Insulation
|
2/26/2026
|
Partial Approval
|
DAVID TSAU
|
|
Drywall Nailing
|
3/3/2026
|
Not Ready for Inspection
|
DAVID TSAU
|
|
Green Building Rough
|
3/3/2026
|
Partial Approval
|
DAVID TSAU
|
|
Wood Frame
|
3/3/2026
|
Partial Approval
|
DAVID TSAU
|
|
Drywall Nailing
|
3/9/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Insulation
|
3/10/2026
|
Partial Approval
|
MICHAEL PETRUSKO
|
|
Insulation
|
3/23/2026
|
Partial Approval
|
DAVID TSAU
|
|
Drywall Nailing
|
3/26/2026
|
Partial Approval
|
DAVID TSAU
|
|
Insulation
|
4/6/2026
|
Partial Approval
|
DAVID TSAU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/30/2026
|
Not Ready for Inspection
|
MICHAEL PETRUSKO
|
|
Green Building Rough
|
4/30/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Wood Frame
|
4/30/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Special/Order Compliance
|
5/6/2026
|
Approved
|
MICHAEL PETRUSKO
|
|
Interior/Exterior Lathing
|
5/11/2026
|
Partial Inspection
|
DAVID TSAU
|
|
Drywall Nailing
|
6/2/2026
|
Partial Approval
|
DAVID TSAU
|