1407 W CARSON ST 90501

Certificate Information: 1407 W CARSON ST 90501

Application / Permit
21010-10000-04430
Plan Check / Job No.
B21LA16093
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5-STORY, 55-UNIT (5 VLI UNITS) AFFORDABLE HOUSING APARTMENT. 4 LEVELS OF TYPE VA APARTMENT OVER 1 LEVEL OF TYPE IA APARTMENT/PARKING.
Permit Issued
Issued on 5/24/2023
Issuing Office
Metro
Current Status
Issued on 5/24/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Green Plans Picked Up 9/8/2021 APPLICANT
Disabled Access Plans Picked Up 9/14/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 LARRY LEE
Corrections Issued 9/27/2021 LARRY LEE
Quality Review Completed 9/30/2021 SAI KHUM
Building Plans Picked Up 10/13/2021 APPLICANT
Applicant returned to address corrections 12/9/2021 LARRY LEE
Applicant returned to address corrections 4/12/2022 LARRY LEE
Applicant returned to address corrections 8/9/2022 LARRY LEE
Plan Check Approved 5/24/2023 KEVIN MORALES
Issued 5/24/2023 APPLICANT

Permit Application Clearance Information

Site Plan review Cleared 9/30/2021 RUBEN VASQUEZ
Hydrant and Access approval Cleared 10/11/2021 ROBERT DUFF
Permit Cleared 10/28/2021 ERIK BEASLEY
Highway dedication Cleared 8/12/2022 ERIK BEASLEY
Address approval Cleared 9/1/2022 ERIK BEASLEY
Comm Cor/Mini-Mall Cleared 10/6/2022 ANACANY HURTADO
Comm Cor/Mini-Mall Cleared 10/6/2022 ANACANY HURTADO
Comm Cor/Mini-Mall Cleared 10/6/2022 ANACANY HURTADO
Low Impact Development Cleared 10/16/2022 MARTIN FRAGOSO
Work Adjacent to Public Way Cleared 11/17/2022 LARRY LEE
Trees in Parkway Cleared 12/12/2022 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 12/30/2022 ERIK BEASLEY
Building over 36-ft Cleared 1/8/2023 CALOSHA APPROVED
Green Code Cleared 1/24/2023 AARON COSTA
Fire Marshal Fire Life Safety Cleared 1/31/2023 MENOA AGHAJANI
DAS Clearance Cleared 2/2/2023 SHINE LIN
DCP conditions approval Cleared 4/6/2023 RICHARD TRUONG
Density Bonus 12.22.A.25 Cleared 4/6/2023 RICHARD TRUONG
Sewer availability Cleared 4/14/2023 KHAING AYE
"Q" conditions Cleared 5/3/2023 MAXFIELD VERMY
Miscellaneous Cleared 5/3/2023 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 5/3/2023 MAXFIELD VERMY
Prkng lot landscape/Water mgmt Cleared 5/3/2023 MAXFIELD VERMY
ZA Case Cleared 5/3/2023 MAXFIELD VERMY

Contact Information

Architect Ashai,, Athar; Lic. No.: C26787 2173 LOMITA BLVD SUITE 201      LOMITA, CA 90717
Contractor Seahawk Construction; Lic. No.: 767212-B 23910 NARBONNE AVE   STE #101    LOMITA, CA 90717
Engineer Dedmari,, Wajahat Hafiz; Lic. No.: C66819 5541 GRAYLOG ST      RANCHO PALOS VERDES, CA 90275

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/3/2023 Corrections Issued AMANUEL BERHE
Footing/Foundation/Slab 10/23/2023 Corrections Issued JOEY BUCHANAN
Footing/Foundation/Slab 11/7/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 11/13/2023 Approved JOEY BUCHANAN
Pre-Inspection 11/13/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 11/14/2023 Approved JOEY BUCHANAN
Footing/Foundation/Slab 12/4/2023 Not Ready for Inspection JOEY BUCHANAN
Deputy Drilled-In Anchors 12/6/2023 Approved JOEY BUCHANAN
Footing/Foundation/Slab 12/6/2023 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 12/13/2023 Approved JOEY BUCHANAN
Green Building Rough 12/29/2023 Off-Hour Fees Due
Reinforced Concrete Frame 12/29/2023 Off-Hour Fees Due
Verify Sprinkler Sign Off 12/29/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 1/16/2024 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 1/17/2024 Approved JOEY BUCHANAN
Special/Order Compliance 2/15/2024 Approved JOEY BUCHANAN
Special/Order Compliance 2/21/2024 Approved JOEY BUCHANAN
Footing/Foundation/Slab 4/26/2024 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 5/2/2024 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 5/10/2024 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 5/17/2024 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 5/17/2024 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 5/21/2024 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 6/10/2024 Partial Approval JOEY BUCHANAN
Pre-Inspection 7/31/2024 Approved AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 9/13/2024 Not Ready for Inspection AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 9/17/2024 Conditional Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 9/23/2024 Not Ready for Inspection AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 9/26/2024 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 10/7/2024 Partial Approval JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 10/28/2024 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 12/10/2024 Conditional Approval JOEY BUCHANAN
Deputy Wood Construction 12/20/2024 Conditional Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Corrections Issued JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 1/9/2025 Partial Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 1/23/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Partial Approval JOEY BUCHANAN
Insulation 5/15/2025 Partial Approval MICHAEL PETRUSKO
Insulation 6/2/2025 Partial Approval RICARDO ROBLES
Insulation 6/11/2025 Partial Approval RICARDO ROBLES
Pre-Inspection 7/25/2025 Partial Approval RICARDO ROBLES
Pre-Inspection 7/31/2025 Partial Approval RICARDO ROBLES
Insulation 8/5/2025 Partial Approval RICARDO ROBLES
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Partial Approval RICARDO ROBLES
Insulation 8/22/2025 Partial Approval RICARDO ROBLES
Insulation 8/26/2025 Partial Approval RICARDO ROBLES
Interior/Exterior Lathing 9/17/2025 Corrections Issued RICARDO ROBLES
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Partial Approval DAVID TSAU
Pre-Inspection 11/24/2025 Partial Approval RICARDO ROBLES
Green Building Rough 1/22/2026 Not Ready for Inspection RICARDO ROBLES
Insulation 1/22/2026 Not Ready for Inspection RICARDO ROBLES
Verify Sprinkler Sign Off 1/22/2026 Not Ready for Inspection RICARDO ROBLES
Wood Frame 1/22/2026 Not Ready for Inspection RICARDO ROBLES
Green Building Rough 1/23/2026 Partial Approval RICARDO ROBLES
Insulation 1/23/2026 Not Ready for Inspection RICARDO ROBLES
Verify Sprinkler Sign Off 1/23/2026 Partial Approval RICARDO ROBLES
Wood Frame 1/23/2026 Partial Approval RICARDO ROBLES
Insulation 1/27/2026 Partial Approval MICHAEL PETRUSKO
Green Building Rough 2/2/2026 Partial Approval DAVID TSAU
Verify Sprinkler Sign Off 2/2/2026 Partial Approval MICHAEL PETRUSKO
Wood Frame 2/2/2026 Partial Approval DAVID TSAU
Drywall Nailing 2/3/2026 Partial Approval DAVID TSAU
Pre-Inspection 2/3/2026 Not Ready for Inspection DAVID TSAU
Green Building Rough 2/5/2026 Partial Approval DAVID TSAU
Pre-Inspection 2/5/2026 Approved DAVID TSAU
Verify Sprinkler Sign Off 2/5/2026 Approved DAVID TSAU
Green Building Rough 2/11/2026 Partial Approval DAVID TSAU
Insulation 2/11/2026 Partial Approval DAVID TSAU
Wood Frame 2/11/2026 Partial Approval DAVID TSAU
Drywall Nailing 2/19/2026 Partial Approval DAVID TSAU
Insulation 2/23/2026 Partial Approval DAVID TSAU
Drywall Nailing 2/26/2026 Partial Approval DAVID TSAU
Insulation 2/26/2026 Partial Approval DAVID TSAU
Drywall Nailing 3/3/2026 Not Ready for Inspection DAVID TSAU
Green Building Rough 3/3/2026 Partial Approval DAVID TSAU
Wood Frame 3/3/2026 Partial Approval DAVID TSAU
Drywall Nailing 3/9/2026 Partial Approval MICHAEL PETRUSKO
Insulation 3/10/2026 Partial Approval MICHAEL PETRUSKO
Insulation 3/23/2026 Partial Approval DAVID TSAU
Drywall Nailing 3/26/2026 Partial Approval DAVID TSAU
Insulation 4/6/2026 Partial Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Not Ready for Inspection MICHAEL PETRUSKO
Green Building Rough 4/30/2026 Approved MICHAEL PETRUSKO
Wood Frame 4/30/2026 Approved MICHAEL PETRUSKO
Special/Order Compliance 5/6/2026 Approved MICHAEL PETRUSKO
Interior/Exterior Lathing 5/11/2026 Partial Inspection DAVID TSAU
Drywall Nailing 6/2/2026 Partial Approval DAVID TSAU