2844 N ROSANNA ST 90039

Certificate Information: 2844 N ROSANNA ST 90039

Application / Permit
21010-10000-04425
Plan Check / Job No.
B21LA16078
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED 680 SF 1-STORY ADU BETWEEN FRONTLOT LINE AND DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(b)(6).
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Corrected on 11/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 VIVIAN LAO
Corrections Issued 10/8/2021 VIVIAN LAO
Quality Review Completed 10/19/2021 MICHAEL PEREZ
Building Plans Picked Up 10/26/2021 APPLICANT
Applicant returned to address corrections 1/11/2022 VIVIAN LAO
Applicant returned to address corrections 3/15/2022 VIVIAN LAO
Plan Check Approved 7/21/2022 VIVIAN LAO
Issued 7/21/2022 APPLICANT
CofO in Progress 10/3/2024 HAMIK HARTOUNIAN
CofO Issued-Status Void 10/28/2024 RUBEN SALAS
Permit Finaled-Status Void 10/28/2024 RUBEN SALAS
Re-Activate Permit 11/26/2024 RUBEN SALAS
Permit Finaled 11/27/2024 RUBEN SALAS
CofO Corrected 11/27/2024 RUBEN SALAS
Permit Finaled 11/27/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/18/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 6/1/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 6/1/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 6/16/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/6/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/7/2022 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 10/27/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 10/31/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 11/28/2022 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/8/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 1/6/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 1/18/2023 Conditional Approval THOMAS LOGRASSO
HVAC-Rough 1/18/2023 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 1/18/2023 Approved THOMAS LOGRASSO
Underground Mechanical 1/18/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/9/2023 Conditional Approval THOMAS LOGRASSO
Green Building Rough 2/9/2023 Approved THOMAS LOGRASSO
HVAC-Rough 2/9/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 2/9/2023 Partial Approval THOMAS LOGRASSO
MERV13>=Rough 2/9/2023 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 2/9/2023 Approved THOMAS LOGRASSO
Insulation 2/13/2023 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 2/15/2023 Approved KATHRYN BUTTERWORTH
Service/Power Release 3/13/2023 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 3/28/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/5/2023 Approved THOMAS LOGRASSO
Final 10/5/2023 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 10/5/2023 Approved THOMAS LOGRASSO
Green Building Final 10/5/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 10/5/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Not Ready THOMAS LOGRASSO
Service/Power Release 10/5/2023 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 10/5/2023 Approved THOMAS LOGRASSO
Final 9/16/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 9/16/2024 Approved HAMIK HARTOUNIAN
MERV13>=Final 9/16/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Approved HAMIK HARTOUNIAN
Final 10/2/2024 OK to Issue CofO HAMIK HARTOUNIAN
Service/Power Release 10/2/2024 Approved HAMIK HARTOUNIAN