4119 W 59TH ST 90043
Certificate Information: 4119 W 59TH ST 90043
- Application / Permit
- 21010-10000-04411
- Plan Check / Job No.
- B21LA16041
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER STATE LAW. WORK PER ENGINEERED DESIGN. **PENDING DEMO PERMIT FOR (E) GARAGE**
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | JOSEPH RAFOLS |
| Corrections Issued | 9/9/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 3/2/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Plan Check Approved | 6/24/2022 | GEORGE ALVAREZ |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 7/31/2024 | JOSE MACIAS |
| CofO in Progress | 7/31/2024 | JOSE MACIAS |
| CofO in Progress | 8/2/2024 | JOSE MACIAS |
| CofO Issued | 9/3/2024 | RUBEN SALAS |
| Permit Finaled | 9/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/4/2021 | RENZ SORIANO |
| Address approval | Cleared | 10/6/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 12/1/2021 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 2/4/2022 | ROBERT HUGHES |
| Construction near power lines | Cleared | 5/12/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/15/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 2/23/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 2/23/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 2/23/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 5/1/2023 | Partial Approval | STUART CHAPMAN |
| Gas Test | 6/15/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/15/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/15/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 6/22/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/22/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/22/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Corrections Issued | ENRIQUE MIRELES |
| Deputy Wood Construction | 7/14/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/29/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 8/29/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 8/29/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 8/29/2023 | Corrections Issued | STUART CHAPMAN |
| METHANE-Rough | 8/29/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 8/29/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 8/29/2023 | Approved | STUART CHAPMAN |
| Insulation | 10/11/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/13/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Not Ready | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/18/2024 | Approved | JOSE MACIAS |
| Final | 7/18/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 7/18/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 7/18/2024 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 7/18/2024 | Approved | JOSE MACIAS |
| Final | 7/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 7/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 7/31/2024 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 7/31/2024 | No Access for Inspection | JOSE MACIAS |