4119 W 59TH ST 90043

Certificate Information: 4119 W 59TH ST 90043

Application / Permit
21010-10000-04411
Plan Check / Job No.
B21LA16041
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT PER STATE LAW. WORK PER ENGINEERED DESIGN. **PENDING DEMO PERMIT FOR (E) GARAGE**
Permit Issued
Issued on 7/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 JOSEPH RAFOLS
Corrections Issued 9/9/2021 JOSEPH RAFOLS
Applicant returned to address corrections 3/2/2022 JOSEPH RAFOLS
Building Plans Picked Up 3/2/2022 APPLICANT
Plan Check Approved 6/24/2022 GEORGE ALVAREZ
Issued 7/28/2022 APPLICANT
CofO in Progress 7/31/2024 JOSE MACIAS
CofO in Progress 7/31/2024 JOSE MACIAS
CofO in Progress 8/2/2024 JOSE MACIAS
CofO Issued 9/3/2024 RUBEN SALAS
Permit Finaled 9/3/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/4/2021 RENZ SORIANO
Address approval Cleared 10/6/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/6/2021 RENZ SORIANO
Sewer availability Cleared 12/1/2021 STEVE MELGAR
Grading Pre-Inspection Cleared 2/4/2022 ROBERT HUGHES
Construction near power lines Cleared 5/12/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 2/15/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/23/2023 Approved ENRIQUE MIRELES
METHANE-Barrier 2/23/2023 Approved ENRIQUE MIRELES
METHANE-Subgrade 2/23/2023 Approved ENRIQUE MIRELES
Sewer 5/1/2023 Partial Approval STUART CHAPMAN
Gas Test 6/15/2023 Approved ENRIQUE MIRELES
Insulation 6/15/2023 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 6/15/2023 Not Ready for Inspection ENRIQUE MIRELES
Gas Test 6/22/2023 Approved ENRIQUE MIRELES
Insulation 6/22/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 6/22/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Corrections Issued ENRIQUE MIRELES
Deputy Wood Construction 7/14/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/14/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 8/29/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/29/2023 Corrections Issued STUART CHAPMAN
Green Building Rough 8/29/2023 Approved STUART CHAPMAN
HVAC-Rough 8/29/2023 Corrections Issued STUART CHAPMAN
METHANE-Rough 8/29/2023 Approved STUART CHAPMAN
PLUMBING-Rough 8/29/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 8/29/2023 Approved STUART CHAPMAN
Insulation 10/11/2023 Approved ENRIQUE MIRELES
Drywall Nailing 10/13/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Not Ready JOSE MACIAS
BUILDING-Rough-Frame 7/18/2024 Approved JOSE MACIAS
Final 7/18/2024 Corrections Issued JOSE MACIAS
Green Building Final 7/18/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Approved JOSE MACIAS
Service/Power Release 7/18/2024 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 7/18/2024 Approved JOSE MACIAS
Final 7/23/2024 Not Ready for Inspection JOSE MACIAS
Service/Power Release 7/23/2024 Not Ready for Inspection JOSE MACIAS
Final 7/31/2024 OK to Issue CofO JOSE MACIAS
Service/Power Release 7/31/2024 No Access for Inspection JOSE MACIAS