1001 E 33RD ST 90011
Certificate Information: 1001 E 33RD ST 90011
- Application / Permit
- 21010-10000-04392
- Plan Check / Job No.
- B21LA15961
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Current Status
- CofO Issued on 7/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/7/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/14/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| Applicant returned to address corrections | 12/9/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 2/1/2022 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 2/25/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/23/2022 | MAHNAZ NOURHASHEMI |
| Issued | 6/8/2022 | APPLICANT |
| CofO in Progress | 7/12/2023 | BRENDAN MORELLI |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| CofO Issued | 7/23/2023 | DEROLD HAUFF |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2021 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 12/16/2021 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 1/14/2022 | TREVOR QUAN |
| Low Impact Development | Cleared | 2/18/2022 | TA ANH |
| Hydrant and Access approval | Cleared | 2/19/2022 | LAURINDA MEADE |
| Permit | Cleared | 2/26/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/26/2022 | JEANETTE VONG |
| Trees in Parkway | Cleared | 4/22/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Ganpat Properties; Lic. No.: 778755-B | 2606 FOOTHILL BLVD SUITE #E LA CRESCENTA, CA 91214 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/12/2022 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 8/18/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/23/2022 | Approved | JOAQUIN GREENOUGH |
| Deputy Steel/Welding | 9/13/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Wood Frame | 9/15/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 10/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 10/14/2022 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 10/14/2022 | Partial Approval | RYAN SALAZAR |
| Sewer | 10/14/2022 | Approved | RYAN SALAZAR |
| Underground Mechanical | 10/14/2022 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 10/14/2022 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 12/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 12/5/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/8/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 12/8/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 12/8/2022 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 12/8/2022 | Not Ready for Inspection | CALEB MEISTER |
| Verify Sprinkler Sign Off | 12/8/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 12/14/2022 | Conditional Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/28/2022 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 12/28/2022 | Not Ready for Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 12/28/2022 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 1/26/2023 | Approved | BRENDAN MORELLI |
| Insulation | 1/26/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/26/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 2/8/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 4/7/2023 | Approved | BRENDAN MORELLI |
| Gas Test | 4/28/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 4/28/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/17/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Final | 5/17/2023 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 5/22/2023 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 5/22/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/31/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Final | 5/31/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 6/21/2023 | Corrections Issued | BRENDAN MORELLI |
| Final | 6/21/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 6/21/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 6/21/2023 | Not Required | BRENDAN MORELLI |
| Smoke Detectors | 6/21/2023 | Approved | BRENDAN MORELLI |
| Final | 7/5/2023 | No Access for Inspection | BRENDAN MORELLI |
| Final | 7/11/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 7/12/2023 | Approved | BRENDAN MORELLI |