6055 N CRANER AVE 1-2 91606
Certificate Information: 6055 N CRANER AVE 1-2 91606
- Application / Permit
- 21010-10000-04389
- Plan Check / Job No.
- B21LA15957
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-STORY FRONT DUPLEX WITH RECREATION ROOM
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 8/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 8/25/2021 | APPLICANT |
Assigned to Plan Check Engineer | 9/30/2021 | DANIEL YIP |
Corrections Issued | 10/7/2021 | DANIEL YIP |
Quality Review Completed | 10/8/2021 | ALLEN MANALANSAN |
Building Plans Picked Up | 10/20/2021 | APPLICANT |
Applicant returned to address corrections | 12/22/2021 | DANIEL YIP |
Applicant returned to address corrections | 5/10/2022 | DANIEL YIP |
Plan Check Approved | 6/9/2022 | DANIEL YIP |
Issued | 6/17/2022 | APPLICANT |
CofO in Progress | 8/15/2023 | JOHN HAYES |
Permit Finaled | 8/25/2023 | RUBEN SALAS |
CofO Issued | 8/25/2023 | RUBEN SALAS |
Permit Finaled | 8/25/2023 | RUBEN SALAS |
Permit Application Clearance Information
Address approval | Cleared | 10/13/2021 | DAGOVERTO GUERRERO |
Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | DAGOVERTO GUERRERO |
Permit | Cleared | 10/13/2021 | DAGOVERTO GUERRERO |
Sewer availability | Cleared | 10/13/2021 | DAGOVERTO GUERRERO |
Hydrant and Access approval | Cleared | 1/4/2022 | GILBERT URREA |
Frnt yard landscape/Water mgmt | Cleared | 1/5/2022 | ERIKA BARBERO |
Opn space landscape/Water mgmt | Cleared | 1/5/2022 | ERIKA BARBERO |
Miscellaneous | Cleared | 1/6/2022 | ERIKA BARBERO |
Low Impact Development | Cleared | 4/15/2022 | TA ANH |
Roof/Waste drainage to street | Cleared | 4/21/2022 | DAGOVERTO GUERRERO |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
JOSE AVILA, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 8/17/2022 | Partial Approval | JOHN HAYES |
Underground Mechanical | 8/17/2022 | Not Ready for Inspection | JOHN HAYES |
Underground Mechanical | 8/18/2022 | Approved | JOHN HAYES |
Footing/Foundation/Slab | 9/7/2022 | Not Ready for Inspection | JOHN HAYES |
Excavation/Setback/Form/Re-Bar | 9/14/2022 | Approved | ALAN MORELOS |
Special/Order Compliance | 9/16/2022 | Approved | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | ALAN MORELOS |
Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Partial Approval | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Partial Approval | JOHN HAYES |
HVAC-Rough | 11/18/2022 | Corrections Issued | CALEB MEISTER |
ELECTRICAL-Rough | 12/14/2022 | Approved | JOHN HAYES |
HVAC-Rough | 12/14/2022 | Not Ready for Inspection | JOHN HAYES |
BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | JOHN HAYES |
Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Partial Approval | JOHN HAYES |
Gas Test | 12/20/2022 | Partial Approval | JOHN HAYES |
HVAC-Rough | 12/20/2022 | Not Ready for Inspection | JOHN HAYES |
PLUMBING-Rough | 12/20/2022 | Approved | JOHN HAYES |
Shower Pan | 12/20/2022 | Approved | JOHN HAYES |
BUILDING-Rough-Frame | 12/27/2022 | Approved | JOHN HAYES |
Green Building Rough | 12/27/2022 | Approved | JOHN HAYES |
Rough-Elec/Plmb/HVAC | 12/27/2022 | Approved | JOHN HAYES |
Verify Sprinkler Sign Off | 12/27/2022 | Approved | JOHN HAYES |
Insulation | 1/3/2023 | Not Ready for Inspection | JOHN HAYES |
Interior/Exterior Lathing | 1/3/2023 | Partial Approval | JOHN HAYES |
Insulation | 1/5/2023 | Approved | JOHN HAYES |
Drywall Nailing | 1/17/2023 | Approved | JOHN HAYES |
Interior/Exterior Lathing | 1/17/2023 | Approved | JOHN HAYES |
Special/Order Compliance | 5/24/2023 | Not Ready for Inspection | JOHN HAYES |
Underground Mechanical | 5/24/2023 | Corrections Issued | JOHN HAYES |
Special/Order Compliance | 5/31/2023 | Off-Hour Fees Due | |
Underground Mechanical | 5/31/2023 | Off-Hour Fees Due | |
Special/Order Compliance | 6/2/2023 | Approved | JOHN HAYES |
Underground Mechanical | 6/2/2023 | Approved | JOHN HAYES |
ELECTRICAL-Final | 7/26/2023 | Partial Approval | DAVID MATSON |
Final | 7/26/2023 | Corrections Issued | DAVID MATSON |
Footing/Foundation/Slab | 7/26/2023 | Approved | DAVID MATSON |
Green Building Final | 7/26/2023 | Approved | DAVID MATSON |
HVAC-Final | 7/26/2023 | Approved | DAVID MATSON |
PLUMBING-Final | 7/26/2023 | Approved | DAVID MATSON |
SGSOV-Seismic Gas S/O Valve | 7/26/2023 | SGSOV Not Ready | DAVID MATSON |
Service/Power Release | 7/26/2023 | Not Ready for Inspection | DAVID MATSON |
Smoke Detectors | 7/26/2023 | Approved | DAVID MATSON |
ELECTRICAL-Final | 8/8/2023 | Not Ready for Inspection | JOHN HAYES |
Final | 8/8/2023 | Corrections Issued | JOHN HAYES |
SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Not Ready | JOHN HAYES |
Service/Power Release | 8/8/2023 | Not Ready for Inspection | JOHN HAYES |
ELECTRICAL-Final | 8/14/2023 | Approved | JOHN HAYES |
Final | 8/14/2023 | OK to Issue CofO | JOHN HAYES |
SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Approved | JOHN HAYES |
Service/Power Release | 8/14/2023 | Approved | JOHN HAYES |