14642 W ADDISON ST 91403
Certificate Information: 14642 W ADDISON ST 91403
- Application / Permit
- 21010-10000-04384
- Plan Check / Job No.
- B21LA15950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New ADU w/ sprinklers
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/30/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/12/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/19/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/4/2021 | HERNAN ARREOLA |
| Issued | 12/7/2021 | APPLICANT |
| CofO in Progress | 3/31/2022 | JACK KARGODORIAN |
| CofO Issued | 5/4/2022 | MICHAEL SMITH |
| Permit Finaled | 5/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/1/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 11/5/2021 | KURT CORRAL |
| Construction within easement | Cleared | 11/21/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Builder Hub Inc; Lic. No.: 976592-B | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/10/2021 | Corrections Issued | JACK KARGODORIAN |
| Pre-Inspection | 12/10/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 12/20/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 12/23/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 2/15/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 2/15/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 2/23/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 2/23/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 2/24/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 2/24/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 2/24/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | JACK KARGODORIAN |
| Final | 3/29/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/29/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 3/29/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 3/29/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 3/29/2022 | Approved | JACK KARGODORIAN |
| Final | 3/31/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 3/31/2022 | Approved | JACK KARGODORIAN |