303 S LUCERNE BLVD 90020

Certificate Information: 303 S LUCERNE BLVD 90020

Application / Permit
21010-10000-04383
Plan Check / Job No.
B21LA15947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO DETACHED GARAGE FOR NEW TWO STORY ADU W/ ATTACHED GARAGE.
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
Issued on 5/19/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 JOE VO
Corrections Issued 10/3/2021 JOE VO
Quality Review Completed 10/14/2021 MICHAEL PEREZ
Applicant returned to address corrections 2/22/2022 JOE VO
Plan Check Approved 3/7/2022 JOE VO
No Progress 4/14/2022 JOE VO
Plan Check Approved 4/14/2022 JOE VO
Issued 5/19/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/28/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/17/2021 STEVE MELGAR
Sewer availability Cleared 11/17/2021 STEVE MELGAR
HPOZ Cleared 1/27/2022 LYDIA CHAPMAN
Historic monument Cleared 1/27/2022 LYDIA CHAPMAN
Low Impact Development Cleared 2/10/2022 TA ANH
Roof/Waste drainage to street Cleared 2/10/2022 WALLIE JONG
Hydrant and Access approval Cleared 2/22/2022 KURT CORRAL

Contact Information

Architect Park,, Yong Keun; Lic. No.: C24806 351 CANON DE PARAISO LN      LA CANADA FLINTRIDGE, CA 91011
Architect Park,, Yong Keun; Lic. No.: NA24806       ,
Contractor L & S Core Construction Inc; Lic. No.: 1026807-B       ,
Engineer Lee,, Sang Youck; Lic. No.: NA3821       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/13/2022 Corrections Issued ADAM ESCOTO
Underground Mechanical 6/17/2022 Approved ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 8/1/2022 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/1/2022 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 8/1/2022 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 8/1/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Inspection JOSEPH MCGARRY
HVAC-Rough 1/19/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 1/19/2023 Approved RICHARD DOCKUS
ELECTRICAL-Rough 2/27/2023 Corrections Issued RICHARD DOCKUS
HVAC-Rough 2/27/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 3/1/2023 Approved RICHARD DOCKUS
Gas Test 3/1/2023 Approved RICHARD DOCKUS
HVAC-Rough 3/1/2023 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 3/1/2023 Approved RICHARD DOCKUS
HVAC-Rough 3/28/2023 Partial Approval MICHAEL LEWIS
Wood Frame 3/28/2023 Not Ready for Inspection MICHAEL LEWIS
Insulation 5/22/2023 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 5/22/2023 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 5/30/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/30/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/30/2023 Partial Approval ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 5/30/2023 Approved ALIZAH MAYAGOITIA
Insulation 6/1/2023 Corrections Issued RICHARD DOCKUS
Insulation 6/6/2023 Approved RICHARD DOCKUS
Drywall Nailing 6/14/2023 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 6/14/2023 Not Ready for Inspection LILIANA PORTILLO
Shower Pan 6/14/2023 Approved LILIANA PORTILLO
Drywall Nailing 6/20/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/20/2023 Partial Approval RICHARD DOCKUS
Interior/Exterior Lathing 6/26/2023 Approved RICHARD DOCKUS
Pre-Inspection 4/17/2024 Approved RONNIE MINDANAO