1405 E 15TH ST 90021

Certificate Information: 1405 E 15TH ST 90021

Application / Permit
21010-10000-04357
Plan Check / Job No.
B21LA15858
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
1 STORY WAREHOUSE W/MEZZANINE AND PARKING. 1 OF 2
Permit Issued
Issued on 10/28/2022
Issuing Office
Current Status
CofO Issued on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 JOE VO
Corrections Issued 10/14/2021 JOE VO
Quality Review Completed 10/14/2021 MICHAEL PEREZ
Disabled Access Plans Picked Up 1/13/2022 APPLICANT
Green Plans Picked Up 5/5/2022 APPLICANT
Building Plans Picked Up 6/15/2022 APPLICANT
Plan Check Approved 7/25/2022 JOE VO
Issued 10/28/2022 APPLICANT
CofO Issued 1/29/2025 ERNESTO CORRAL
Permit Finaled 1/29/2025 ERNESTO CORRAL

Permit Application Clearance Information

Highway dedication Cleared 12/3/2021 JEANIE LAM
Permit Cleared 12/3/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/6/2021 JEANIE LAM
Sewer availability Cleared 12/6/2021 JEANIE LAM
"D" conditions Cleared 12/29/2021 ERIKA BARBERO
Redevelopment Project Area Cleared 12/30/2021 DAVID URITA
DAS Clearance Cleared 1/10/2022 JOE VO
Hydrant and Access approval Cleared 3/9/2022 MATTHEW CRAIG
Trees in Parkway Cleared 4/19/2022 ADALBERTO VERA
Driveway location Cleared 4/21/2022 PETE EYRE
Green Code Cleared 4/21/2022 AARON COSTA
Miscellaneous Cleared 4/21/2022 PETE EYRE
Low Impact Development Cleared 6/22/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/5/2022 TREVOR QUAN

Contact Information

Architect Segal,, Barry William; Lic. No.: C17861 P O BOX 6108      ALTADENA, CA 91003
Contractor Rw Scherrer Inc; Lic. No.: 1063745-B 436 S EAGLES POINT      ORANGE, CA 92869
Engineer Bushra,, Rafeek L; Lic. No.: S4490 2564 W WOODLAND DR      ANAHEIM, CA 92801

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/14/2022 Partial Inspection NICK DANERI
Footing/Foundation/Slab 12/28/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 1/3/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 1/4/2023 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 1/4/2023 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 1/13/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Other (see comments) 3/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 3/21/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/22/2023 Not Ready for Inspection ALFREDO LOPEZ
Reinforced Masonry Frame 3/22/2023 Partial Inspection ALFREDO LOPEZ
Special/Order Compliance 3/22/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/22/2023 Not Ready for Inspection ALFREDO LOPEZ
Deputy Reinf. Masonry 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 3/28/2023 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 3/28/2023 Partial Approval ALFREDO LOPEZ
Masonry Wall/Backfill 3/28/2023 Partial Approval ALFREDO LOPEZ
Deputy Reinf. Masonry 4/3/2023 Conditional Approval GREGORY POMISH
Wood Frame 4/3/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 4/7/2023 Partial Inspection GREGORY POMISH
Deputy Reinf. Masonry 4/11/2023 Conditional Approval LARRY ARNICK
Wood Frame 4/11/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Masonry 4/12/2023 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 4/12/2023 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 4/13/2023 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 4/18/2023 Partial Approval LARRY ARNICK
Wood Frame 4/24/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 5/1/2023 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 5/4/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Approved LARRY ARNICK
Footing/Foundation/Slab 6/2/2023 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 6/20/2023 Approved LARRY ARNICK
Wood Frame 8/30/2023 Partial Approval NICK DANERI
Wood Frame 9/19/2023 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/22/2023 Partial Approval RAFAEL ESPINOZA
Insulation 11/1/2023 Approved NICK DANERI
Drywall Nailing 11/6/2023 Approved NICK DANERI
Footing/Foundation/Slab 2/7/2024 Partial Approval NICK DANERI
Final 8/26/2024 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 8/26/2024 Approved NICK DANERI
Green Building Final 8/26/2024 Not Ready for Inspection NICK DANERI
Green Building Rough 8/26/2024 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 8/26/2024 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Not Ready NICK DANERI
Smoke Detectors 8/26/2024 Approved NICK DANERI
Verify Sprinkler Sign Off 8/26/2024 Not Ready for Inspection NICK DANERI
Final 11/22/2024 Partial Inspection NICK DANERI
Green Building Final 11/22/2024 Not Ready for Inspection NICK DANERI
Green Building Rough 11/22/2024 Approved NICK DANERI
Reinforced Masonry Frame 11/22/2024 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved NICK DANERI
Verify Sprinkler Sign Off 11/22/2024 Approved NICK DANERI
Final 1/6/2025 Conditional Approval NICK DANERI
Green Building Final 1/6/2025 Approved NICK DANERI