1405 E 15TH ST 90021
Certificate Information: 1405 E 15TH ST 90021
- Application / Permit
- 21010-10000-04357
- Plan Check / Job No.
- B21LA15858
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- 1 STORY WAREHOUSE W/MEZZANINE AND PARKING. 1 OF 2
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Current Status
- CofO Issued on 1/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | JOE VO |
| Corrections Issued | 10/14/2021 | JOE VO |
| Quality Review Completed | 10/14/2021 | MICHAEL PEREZ |
| Disabled Access Plans Picked Up | 1/13/2022 | APPLICANT |
| Green Plans Picked Up | 5/5/2022 | APPLICANT |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Plan Check Approved | 7/25/2022 | JOE VO |
| Issued | 10/28/2022 | APPLICANT |
| CofO Issued | 1/29/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/29/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 12/3/2021 | JEANIE LAM |
| Permit | Cleared | 12/3/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2021 | JEANIE LAM |
| Sewer availability | Cleared | 12/6/2021 | JEANIE LAM |
| "D" conditions | Cleared | 12/29/2021 | ERIKA BARBERO |
| Redevelopment Project Area | Cleared | 12/30/2021 | DAVID URITA |
| DAS Clearance | Cleared | 1/10/2022 | JOE VO |
| Hydrant and Access approval | Cleared | 3/9/2022 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 4/19/2022 | ADALBERTO VERA |
| Driveway location | Cleared | 4/21/2022 | PETE EYRE |
| Green Code | Cleared | 4/21/2022 | AARON COSTA |
| Miscellaneous | Cleared | 4/21/2022 | PETE EYRE |
| Low Impact Development | Cleared | 6/22/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/5/2022 | TREVOR QUAN |
Contact Information
| Architect | Segal,, Barry William; Lic. No.: C17861 | P O BOX 6108 ALTADENA, CA 91003 |
| Contractor | Rw Scherrer Inc; Lic. No.: 1063745-B | 436 S EAGLES POINT ORANGE, CA 92869 |
| Engineer | Bushra,, Rafeek L; Lic. No.: S4490 | 2564 W WOODLAND DR ANAHEIM, CA 92801 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2022 | Partial Inspection | NICK DANERI |
| Footing/Foundation/Slab | 12/28/2022 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 1/3/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/4/2023 | Conditional Approval | RAFAEL ESPINOZA |
| Reinforced Concrete Frame | 1/4/2023 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 1/13/2023 | Partial Approval | NICK DANERI |
| Deputy Reinf. Concrete | 1/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Other (see comments) | 3/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Masonry | 3/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 3/22/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Reinforced Masonry Frame | 3/22/2023 | Partial Inspection | ALFREDO LOPEZ |
| Special/Order Compliance | 3/22/2023 | Partial Approval | NICK DANERI |
| Verify Sprinkler Sign Off | 3/22/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Deputy Reinf. Masonry | 3/23/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Masonry | 3/28/2023 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 3/28/2023 | Partial Approval | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 3/28/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Masonry | 4/3/2023 | Conditional Approval | GREGORY POMISH |
| Wood Frame | 4/3/2023 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 4/7/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Masonry | 4/11/2023 | Conditional Approval | LARRY ARNICK |
| Wood Frame | 4/11/2023 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Reinf. Masonry | 4/12/2023 | Conditional Approval | LARRY ARNICK |
| Masonry Wall/Backfill | 4/12/2023 | Partial Approval | LARRY ARNICK |
| Masonry Wall/Backfill | 4/13/2023 | Partial Approval | LARRY ARNICK |
| Masonry Wall/Backfill | 4/18/2023 | Partial Approval | LARRY ARNICK |
| Wood Frame | 4/24/2023 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 5/1/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 5/4/2023 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Approved | LARRY ARNICK |
| Footing/Foundation/Slab | 6/2/2023 | Partial Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 6/20/2023 | Approved | LARRY ARNICK |
| Wood Frame | 8/30/2023 | Partial Approval | NICK DANERI |
| Wood Frame | 9/19/2023 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 9/22/2023 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 11/1/2023 | Approved | NICK DANERI |
| Drywall Nailing | 11/6/2023 | Approved | NICK DANERI |
| Footing/Foundation/Slab | 2/7/2024 | Partial Approval | NICK DANERI |
| Final | 8/26/2024 | Not Ready for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 8/26/2024 | Approved | NICK DANERI |
| Green Building Final | 8/26/2024 | Not Ready for Inspection | NICK DANERI |
| Green Building Rough | 8/26/2024 | Not Ready for Inspection | NICK DANERI |
| Reinforced Masonry Frame | 8/26/2024 | Not Ready for Inspection | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Not Ready | NICK DANERI |
| Smoke Detectors | 8/26/2024 | Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 8/26/2024 | Not Ready for Inspection | NICK DANERI |
| Final | 11/22/2024 | Partial Inspection | NICK DANERI |
| Green Building Final | 11/22/2024 | Not Ready for Inspection | NICK DANERI |
| Green Building Rough | 11/22/2024 | Approved | NICK DANERI |
| Reinforced Masonry Frame | 11/22/2024 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 11/22/2024 | Approved | NICK DANERI |
| Final | 1/6/2025 | Conditional Approval | NICK DANERI |
| Green Building Final | 1/6/2025 | Approved | NICK DANERI |