2505 1/2 S RIMPAU BLVD 90016

Certificate Information: 2505 1/2 S RIMPAU BLVD 90016

Application / Permit
21010-10000-04284
Plan Check / Job No.
B21LA15547
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 6/6/2022
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 DANIEL YIP
Corrections Issued 9/14/2021 DANIEL YIP
Quality Review Completed 9/20/2021 JASON HEALEY
Plan Check Approved 3/15/2022 DANIEL YIP
Issued 6/6/2022 APPLICANT
Building Plans Picked Up 6/10/2022 APPLICANT
CofO in Progress 3/22/2024 JUSTIN HAWLEY
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 11/19/2021 CHRIS VONG
Address approval Cleared 12/6/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/6/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/13/2021 AMAAN MALIK
Sewer availability Cleared 12/13/2021 AMAAN MALIK
Hydrant and Access approval Cleared 3/4/2022 DWAYNE LAURENT

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2022 Approved STUART CHAPMAN
PLUMBING-Rough 2/8/2023 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 2/17/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 5/5/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 5/5/2023 Corrections Issued CALEB MEISTER
Green Building Rough 5/5/2023 Not Ready for Inspection CALEB MEISTER
MERV13>=Rough 5/5/2023 Approved CALEB MEISTER
PLUMBING-Rough 5/5/2023 Approved CALEB MEISTER
Verify Sprinkler Sign Off 5/5/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 6/8/2023 Corrections Issued CALEB MEISTER
Green Building Rough 6/8/2023 Not Ready for Inspection CALEB MEISTER
Shower Pan 6/8/2023 Not Ready for Inspection CALEB MEISTER
Verify Sprinkler Sign Off 6/8/2023 Not Ready for Inspection CALEB MEISTER
Insulation 6/29/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 6/29/2023 Approved CALEB MEISTER
Shower Pan 6/29/2023 Approved CALEB MEISTER
Drywall Nailing 7/14/2023 Approved CALEB MEISTER
Green Building Rough 7/14/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 2/15/2024 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 2/15/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 2/15/2024 Approved JUSTIN HAWLEY
Final 2/15/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 2/15/2024 Approved JUSTIN HAWLEY
HVAC-Final 2/15/2024 Approved JUSTIN HAWLEY
MERV13>=Final 2/15/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 2/15/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 2/15/2024 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 2/15/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 3/22/2024 Approved JUSTIN HAWLEY
Final 3/22/2024 OK to Issue CofO JUSTIN HAWLEY
Service/Power Release 3/22/2024 Approved JUSTIN HAWLEY