1654-1656 W 35TH ST 90018
Certificate Information: 1654-1656 W 35TH ST 90018
- Application / Permit
- 21010-10000-04282
- Plan Check / Job No.
- B21LA15544
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- CofO Issued on 7/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | DANIEL YIP |
| Corrections Issued | 9/14/2021 | DANIEL YIP |
| Quality Review Completed | 9/17/2021 | JASON HEALEY |
| Plan Check Approved | 4/5/2022 | DANIEL YIP |
| Issued | 4/14/2022 | APPLICANT |
| CofO in Progress | 7/11/2023 | SABAS ALONSO |
| Permit Finaled | 7/20/2023 | DEROLD HAUFF |
| CofO Issued | 7/20/2023 | DEROLD HAUFF |
| Permit Finaled | 7/20/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2022 | CINDY QI |
| Permit | Cleared | 1/13/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | CINDY QI |
| Sewer availability | Cleared | 1/18/2022 | CINDY QI |
| Frnt yard landscape/Water mgmt | Cleared | 1/27/2022 | DANIEL CORONADO |
| Trees in Parkway | Cleared | 2/16/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/8/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/9/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 3/23/2022 | GILBERT URREA |
Contact Information
| Contractor | Luban Z Construction Corp; Lic. No.: 1033129-B | 16972 NAZARE DR CHINO HILLS, CA 91709 |
| Engineer | Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 | PO BOX 5044 PASADENA, CA 91117 |
| Geologist | Kaligi,, Azad Adam; Lic. No.: GEO9287 | 445 S FIGEUROA ST 3100 LOS ANGELES, CA 90071 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 6/21/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 6/21/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 6/30/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 6/30/2022 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 7/12/2022 | Approved | SABAS ALONSO |
| METHANE-Barrier | 7/12/2022 | Approved | SABAS ALONSO |
| Deputy Steel/Welding | 8/2/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 9/15/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Partial Approval | SABAS ALONSO |
| Sewer | 10/28/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 11/10/2022 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 11/10/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 11/16/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 11/16/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/16/2022 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 12/9/2022 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/13/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/13/2022 | Approved | SABAS ALONSO |
| METHANE-Rough | 12/13/2022 | Approved | SABAS ALONSO |
| Pre-Inspection | 12/13/2022 | Partial Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/13/2022 | Approved | SABAS ALONSO |
| Insulation | 12/19/2022 | Corrections Issued | HORACE FULTZ |
| Insulation | 12/21/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/21/2022 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 1/5/2023 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 1/9/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/31/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 4/21/2023 | Approved | SABAS ALONSO |
| Gas Test | 4/21/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 4/26/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/26/2023 | Approved | SABAS ALONSO |
| Final | 6/14/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/14/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 6/14/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/14/2023 | Approved | SABAS ALONSO |
| Final | 7/10/2023 | OK to Issue CofO | SABAS ALONSO |