5710 W PACKARD ST 90019
Certificate Information: 5710 W PACKARD ST 90019
- Application / Permit
- 21010-10000-04280
- Plan Check / Job No.
- B21LA15541
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
- Permit Issued
- Issued on 6/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | DANIEL YIP |
| Corrections Issued | 9/14/2021 | DANIEL YIP |
| Quality Review Completed | 9/17/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| Applicant returned to address corrections | 1/27/2022 | DANIEL YIP |
| Plan Check Approved | 4/15/2022 | DANIEL YIP |
| Issued | 6/22/2022 | APPLICANT |
| CofO in Progress | 3/27/2024 | ENRIQUE MIRELES |
| Permit Finaled | 3/29/2024 | RONALD MYRICK |
| CofO Issued | 3/29/2024 | RONALD MYRICK |
| Permit Finaled | 3/29/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2021 | RENZ SORIANO |
| Address approval | Cleared | 10/13/2021 | RENZ SORIANO |
| Permit | Cleared | 10/13/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/14/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 12/9/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 1/21/2022 | GILBERT URREA |
Contact Information
| Architect | Musolino,, John Michael; Lic. No.: C33574 | 1200 OPAL STREET # 22 REDONDO BEACH, CA 90277 |
| Contractor | Hop To It Construction Inc; Lic. No.: 1090782-B | 24212 OCEAN AVE TORRANCE, CA 90505 |
| Engineer | Trevellin,, Maurizio; Lic. No.: C71368 | 707 ASHLAND AVE 2 SANTA MONICA, CA 90405 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Subgrade | 11/14/2022 | Approved | JOSE AVILA |
| Sewer | 11/14/2022 | Approved | JOSE AVILA |
| Underground Mechanical | 11/14/2022 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 11/22/2022 | Approved | MICHAEL LEWIS |
| Sewer | 11/22/2022 | Partial Approval | MICHAEL LEWIS |
| Reinforced Concrete Frame | 11/30/2022 | Approved | JOSE AVILA |
| Sewer | 11/30/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/23/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 2/23/2023 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 2/23/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 2/23/2023 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/6/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 3/6/2023 | Approved | JOSE AVILA |
| METHANE-Rough | 3/6/2023 | Approved | JOSE AVILA |
| Green Building Rough | 3/10/2023 | Approved | JOSE AVILA |
| Insulation | 3/10/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 6/28/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 6/28/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/4/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 12/4/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 12/4/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 12/4/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/4/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 12/4/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 12/4/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 12/11/2023 | Corrections Issued | RONNIE MINDANAO |
| Final | 12/11/2023 | Corrections Issued | RONNIE MINDANAO |
| Service/Power Release | 12/11/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/19/2023 | Approved | RONNIE MINDANAO |
| Final | 12/19/2023 | Corrections Issued | RONNIE MINDANAO |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 3/26/2024 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 3/26/2024 | Approved | ENRIQUE MIRELES |