4431 W GAINSBOROUGH AVE 90027
Certificate Information: 4431 W GAINSBOROUGH AVE 90027
- Application / Permit
- 21010-10000-04274
- Plan Check / Job No.
- B21LA15520
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- First and second story addition to an (E) detached 2-car garage and conversion of new addition into an ADU per ordinance 186,481.
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2021 | HELEN NGUYEN |
| Corrections Issued | 8/26/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/15/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/30/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/2/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/17/2021 | HELEN NGUYEN |
| Issued | 12/21/2021 | APPLICANT |
| CofO in Progress | 1/13/2023 | JOSEPH MCGARRY |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
| CofO Issued | 1/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 9/29/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 9/29/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 11/10/2021 | ALEXANDER HELFER |
Contact Information
| Contractor | Green Avenues; Lic. No.: 1052275-B | , |
| Engineer | Charifa,, Rizaldy Dizon; Lic. No.: C62585 | 815 W CESAR E CHAVEZ AVE STE 205 LOS ANGELES, CA 90012 |
| Engineer | Charifa,, Rizaldy Dizon; Lic. No.: NA62585 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Corrections Issued | JOSEPH MCGARRY |
| Pre-Inspection | 2/28/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/2/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/14/2022 | Approved | JOSEPH MCGARRY |
| Wood Frame | 4/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 5/9/2022 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/12/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 5/12/2022 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/13/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/13/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/5/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 7/5/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 7/5/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/22/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 7/22/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/22/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/29/2022 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 7/29/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 8/22/2022 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/4/2022 | Approved | JOSEPH MCGARRY |
| Sewer | 11/4/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 11/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 11/16/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/22/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 12/22/2022 | Approved | JOSEPH MCGARRY |
| Final | 12/22/2022 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 12/22/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 1/6/2023 | OK to Issue CofO | JOSEPH MCGARRY |
| Smoke Detectors | 1/6/2023 | Approved | JOSEPH MCGARRY |