636-636 1/2 E VERNON AVE 90011
Certificate Information: 636-636 1/2 E VERNON AVE 90011
- Application / Permit
- 21010-10000-04238
- Plan Check / Job No.
- B21LA15424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY DUPLEX WITH ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). FIRE SPRINKLER 13D THROUGH OUT.
- Permit Issued
- Issued on 2/27/2026
- Issuing Office
- Current Status
- Issued on 2/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | DANIEL YIP |
| Corrections Issued | 9/14/2021 | DANIEL YIP |
| Quality Review Completed | 9/17/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| Plan Check Approved | 1/21/2022 | DANIEL YIP |
| Issued | 2/27/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | TREVOR QUAN |
| Sewer availability | Cleared | 11/30/2021 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | TREVOR QUAN |
| Sewer availability | Cleared | 12/1/2021 | TREVOR QUAN |
| Frnt yard landscape/Water mgmt | Cleared | 12/10/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 12/14/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/15/2021 | TREVOR QUAN |
| Redevelopment Project Area | Cleared | 12/16/2021 | GRACIELA ACOSTA |
| Hydrant and Access approval | Cleared | 1/15/2022 | RUEL COLE |
| Address approval | Cleared | 11/12/2024 | TREVOR QUAN |
| DAS Clearance | Cleared | 2/27/2026 | DANIEL YIP |
| Hold | Cleared | 5/11/2026 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/13/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/14/2026 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/22/2026 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2026 | Approved | JOHN QUINTANILLA |