1629-1631 S BEDFORD ST 90035
Certificate Information: 1629-1631 S BEDFORD ST 90035
- Application / Permit
- 21010-10000-04235
- Plan Check / Job No.
- B21LA15405
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX/W ATT GARAGE WITH ROOF DECK
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- Issued on 5/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | CARLOS MONTES |
| Corrections Issued | 12/1/2021 | CARLOS MONTES |
| Quality Review Completed | 12/8/2021 | KEN GILL |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| Applicant returned to address corrections | 8/24/2022 | CARLOS MONTES |
| Plan Check Approved | 5/1/2024 | CARLOS MONTES |
| Issued | 5/3/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 6/1/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 6/28/2022 | ADALBERTO VERA |
| Permit | Cleared | 7/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 7/15/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 7/29/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/16/2022 | AMAAN MALIK |
Contact Information
| Contractor | Ponderosa Pines Gen Contractors; Lic. No.: 450947-B | 9616 RIESHEL STREET PICO RIVERA, CA 90660 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Sewer | 6/4/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 7/8/2024 | Corrections Issued | SEAN HAUPT |
| METHANE-Barrier | 7/8/2024 | Not Ready for Inspection | SEAN HAUPT |
| METHANE-Subgrade | 7/8/2024 | Not Ready for Inspection | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/12/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Barrier | 7/12/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 7/12/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/24/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Subgrade | 7/24/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Piling/Pier/Caisson | 7/24/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 8/9/2024 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/9/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 8/9/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Final | 8/9/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 8/9/2024 | Approved | MEL KHACHATOURIAN |
| Piling/Pier/Caisson | 8/9/2024 | Approved | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 8/12/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/30/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 9/4/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 9/4/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/23/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 12/24/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 12/24/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Partial Approval | MEL KHACHATOURIAN |
| Pre-Inspection | 12/26/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/25/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 3/21/2025 | Corrections Issued | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/21/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/26/2025 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 3/26/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 3/26/2025 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 3/26/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 3/27/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | EVAN COOPER |
| Shower Pan | 3/28/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/25/2025 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 4/29/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Approved | EVAN COOPER |
| Green Building Rough | 4/30/2025 | Approved | EVAN COOPER |
| Insulation | 4/30/2025 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 4/30/2025 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/30/2025 | Approved | EVAN COOPER |
| Insulation | 6/4/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 6/26/2025 | Approved | EVAN COOPER |