Pre-Inspection
|
10/20/2022
|
Partial Inspection
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
10/24/2022
|
Corrections Issued
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
10/27/2022
|
Partial Approval
|
ROBERT DAVIS
|
|
Light Gage Steel Frame
|
11/14/2022
|
Partial Inspection
|
ROBERT DAVIS
|
|
Pre-Inspection
|
11/14/2022
|
Approved
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
11/18/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
11/21/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
11/21/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
11/21/2022
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
12/1/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
12/1/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Drilled-In Anchors
|
12/2/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
12/2/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
12/2/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
12/2/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
12/5/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
12/5/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
12/5/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
12/6/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
12/6/2022
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
12/7/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
12/7/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
12/8/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
12/8/2022
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
12/9/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
12/9/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Footing/Foundation/Slab
|
12/9/2022
|
Partial Approval
|
CAMERON CHABAN
|
|
Reinforced Concrete Frame
|
12/9/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Grading Pre-Inspection
|
12/10/2022
|
No Result Entered
|
DANNY RODRIGUEZ
|
|
Deputy Other (see comments)
|
12/12/2022
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Reinf. Concrete
|
12/12/2022
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Other (see comments)
|
12/14/2022
|
Partial Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Masonry
|
12/14/2022
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Shotcrete
|
12/14/2022
|
Partial Approval
|
ANDREW DORSO
|
|
Footing/Foundation/Slab
|
12/17/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
12/22/2022
|
Partial Inspection
|
ANDREW DORSO
|
|
Deputy Other (see comments)
|
12/23/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
12/23/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Other (see comments)
|
12/28/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
12/28/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Other (see comments)
|
12/30/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
12/30/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Reinforced Concrete Frame
|
12/30/2022
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
1/3/2023
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
1/4/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Drilled-In Anchors
|
1/20/2023
|
Approved
|
JOHN KITCKO
|
|
Deputy Other (see comments)
|
1/20/2023
|
Approved
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
1/23/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
1/24/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
1/24/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
1/25/2023
|
Conditional Approval
|
ANDREW DORSO
|
|
Special/Order Compliance
|
1/25/2023
|
Conditional Approval
|
STEVEN LEVITT
|
|
Deputy Other (see comments)
|
1/26/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
1/26/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/26/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
1/26/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
1/27/2023
|
Approved
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
1/27/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
1/27/2023
|
Approved
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
1/27/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
1/30/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/30/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
1/30/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Drilled-In Anchors
|
2/1/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
2/2/2023
|
Approved
|
ROBERT DAVIS
|
|
Green Building Rough
|
2/2/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
2/2/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
2/2/2023
|
Partial Inspection
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
2/6/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/8/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/9/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/9/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/9/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
2/9/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
2/9/2023
|
Approved
|
BRIAN KELLY
|
|
Deputy Other (see comments)
|
2/10/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/10/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/10/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/13/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/14/2023
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
2/14/2023
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
2/15/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/15/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/16/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/16/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/16/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/17/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/17/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/17/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/21/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/21/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
2/21/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/22/2023
|
Approved
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/22/2023
|
Approved
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/22/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
2/22/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/7/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/8/2023
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
3/9/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/10/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/14/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
3/15/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/16/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/16/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/17/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/17/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
3/17/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
3/20/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
3/20/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/20/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/20/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/21/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/23/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/23/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/24/2023
|
Approved
|
ROBERT DAVIS
|
|
Green Building Rough
|
3/24/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
3/24/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
3/24/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Drilled-In Anchors
|
3/28/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
3/28/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
3/28/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/28/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
3/28/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/29/2023
|
No Access for Inspection
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/29/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
3/29/2023
|
Approved
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/30/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
3/31/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
3/31/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
4/5/2023
|
Approved
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/5/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
4/5/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
4/6/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/6/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/7/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/10/2023
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
4/11/2023
|
Approved
|
ROBERT DAVIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/11/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
4/11/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
4/11/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/12/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/13/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/14/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/17/2023
|
Approved
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
4/17/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
4/18/2023
|
Approved
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/18/2023
|
Approved
|
ROBERT DAVIS
|
|
Green Building Rough
|
4/18/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
4/18/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
4/18/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/20/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
4/20/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
4/20/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Masonry Wall/Backfill
|
4/20/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/21/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
4/21/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/25/2023
|
Approved
|
ROBERT DAVIS
|
|
Green Building Rough
|
4/25/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
4/25/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
4/25/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/26/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
4/27/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/27/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
4/28/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
5/2/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
5/3/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
5/3/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Insulation
|
5/3/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
5/3/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Wood Construction
|
5/4/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
5/9/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Wood Frame
|
5/9/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
5/10/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
5/17/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
5/19/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Green Building Rough
|
5/19/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
5/19/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Wood Frame
|
5/19/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
5/23/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
5/23/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
5/25/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
5/30/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
6/2/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Insulation
|
6/2/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Wood Frame
|
6/2/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
6/5/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
6/9/2023
|
Approved
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
6/9/2023
|
Approved
|
ROBERT DAVIS
|
|
Wood Frame
|
6/9/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
6/13/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Drywall Nailing
|
6/16/2023
|
OK to Expire Permit
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
6/21/2023
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
6/27/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
6/27/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
7/17/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
7/20/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
7/20/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Excavation/Setback/Form/Re-Bar
|
7/25/2023
|
Partial Approval
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
7/25/2023
|
Partial Inspection
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
9/18/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
9/19/2023
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
9/20/2023
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
9/22/2023
|
Conditional Approval
|
ROBERT DAVIS
|
|
Pre-Inspection
|
9/27/2023
|
Approved
|
ROBERT DAVIS
|
|
Final
|
10/13/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
10/13/2023
|
Approved
|
ROBERT DAVIS
|
|
Green Building Final
|
10/13/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
SGSOV-Seismic Gas S/O Valve
|
10/13/2023
|
SGSOV Approved
|
ROBERT DAVIS
|
|
Smoke Detectors
|
10/13/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Wood Frame
|
10/13/2023
|
Approved
|
ROBERT DAVIS
|
|
Final
|
10/18/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Green Building Final
|
10/18/2023
|
Approved
|
ROBERT DAVIS
|
|
Smoke Detectors
|
10/18/2023
|
Approved
|
ROBERT DAVIS
|
|
Final
|
11/15/2023
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/1/2024
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/2/2024
|
Conditional Approval
|
ROBERT DAVIS
|
|
Final
|
2/27/2024
|
OK to Issue CofO
|
ROBERT DAVIS
|