3000 S CASTLE HEIGHTS AVE 90034
Certificate Information: 3000 S CASTLE HEIGHTS AVE 90034
- Application / Permit
- 21010-10000-04219
- Plan Check / Job No.
- B21LA15379
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | DANIEL YIP |
| Corrections Issued | 9/20/2021 | DANIEL YIP |
| Quality Review Completed | 9/24/2021 | JASON HEALEY |
| Applicant returned to address corrections | 2/1/2022 | DANIEL YIP |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| Plan Check Approved | 6/24/2022 | DANIEL YIP |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 8/20/2024 | ASHLEY THOMPSON |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
| CofO Issued | 8/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 1/19/2022 | ANDREW SLUSSER |
| ZA Case | Cleared | 1/26/2022 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 3/2/2022 | CINDY JOSSELYN |
| GPI Written Notices | Cleared | 4/20/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 4/20/2022 | DANIEL YIP |
| Low Impact Development | Cleared | 6/10/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/23/2022 | DINAH GARIN |
Contact Information
| Contractor | Zohrabians Construction Company; Lic. No.: 1075123-B | 1367 FOOTHILL BLVD LA CANADA FLINTRIDGE, CA 91011 |
| Engineer | Ha,, Seungil; Lic. No.: S4164 | 3454 W 1ST ST LOS ANGELES, CA 90004 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/12/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 10/4/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 5/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 5/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/10/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/19/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 5/19/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 5/19/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 5/30/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 5/30/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 5/30/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 6/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 6/14/2023 | Conditional Approval | HERBERT GIRON |
| Insulation | 6/20/2023 | Corrections Issued | DAVID FEILER |
| Insulation | 6/22/2023 | Approved | DAVID FEILER |
| Drywall Nailing | 6/28/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 6/28/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/25/2023 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 9/5/2023 | Partial Approval | BEN MOLSTAD |
| Sewer | 9/25/2023 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 4/29/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 6/20/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 6/20/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 6/28/2024 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/29/2024 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 7/29/2024 | Approved | ASHLEY THOMPSON |
| Final | 7/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 7/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 7/29/2024 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/29/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Service/Power Release | 7/29/2024 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 7/29/2024 | Approved | ASHLEY THOMPSON |
| Final | 8/2/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 8/2/2024 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 8/2/2024 | Partial Inspection | REGINA MENDEZ |
| Final | 8/20/2024 | OK to Issue CofO | ASHLEY THOMPSON |