703-703 1/2 W 74TH ST 90044

Certificate Information: 703-703 1/2 W 74TH ST 90044

Application / Permit
21010-10000-04197
Plan Check / Job No.
B21LA15291
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX AT REAR OF LOT WITH ATTACHED 8-CAR GARAGE.
Permit Issued
Issued on 7/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 MAHNAZ NOURHASHEMI
Corrections Issued 9/30/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 10/4/2021 KEN GILL
Building Plans Picked Up 10/6/2021 APPLICANT
Plan Check Approved 5/4/2022 MAHNAZ NOURHASHEMI
Issued 7/27/2022 APPLICANT
CofO in Progress 5/16/2023 MICHAEL LEWIS
Permit Finaled 5/19/2023 DEROLD HAUFF
CofO Issued 5/19/2023 DEROLD HAUFF
Permit Finaled 5/19/2023 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 11/2/2021 RICHARD REASER
Address approval Cleared 1/19/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 1/28/2022 TREVOR QUAN
Sewer availability Cleared 1/28/2022 TREVOR QUAN
Hydrant and Access approval Cleared 3/29/2022 GREGORY HOERNER
Low Impact Development Cleared 3/29/2022 KHAING AYE
Roof/Waste drainage to street Cleared 4/1/2022 KHOUNG LE

Contact Information

Contractor California Realty & Investment Group Inc; Lic. No.: 929543-B PO BOX 40322      DOWNEY, CA 90239
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 8/26/2022 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 8/29/2022 Conditional Approval LILIANA PORTILLO
Special/Order Compliance 8/29/2022 Approved HORACE FULTZ
Deputy Reinf. Concrete 8/31/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 11/17/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 11/17/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 11/21/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 11/21/2022 Corrections Issued LILIANA PORTILLO
Sewer 11/21/2022 Approved LILIANA PORTILLO
Underground Mechanical 11/21/2022 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 11/28/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Corrections Issued LILIANA PORTILLO
Verify Sprinkler Sign Off 11/28/2022 Approved LILIANA PORTILLO
Insulation 12/1/2022 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Not Ready for Inspection LILIANA PORTILLO
Insulation 12/6/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 12/6/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 12/16/2022 Approved LILIANA PORTILLO
Green Building Rough 12/16/2022 Approved LILIANA PORTILLO
Insulation 12/16/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/16/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 3/10/2023 Corrections Issued LILIANA PORTILLO
Final 3/10/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 3/10/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 3/10/2023 Approved LILIANA PORTILLO
HVAC-Final 3/15/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/3/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Final 4/3/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/10/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/10/2023 Approved LILIANA PORTILLO
Final 4/10/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/10/2023 Approved LILIANA PORTILLO
Green Building Final 4/10/2023 Approved LILIANA PORTILLO
Service/Power Release 4/10/2023 Not Ready for Inspection LILIANA PORTILLO
Final 5/15/2023 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 5/15/2023 Approved MICHAEL LEWIS