600 S MORENO AVE 90049
Certificate Information: 600 S MORENO AVE 90049
- Application / Permit
- 21010-10000-04121
- Plan Check / Job No.
- B21LA15013
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) 2 CAR GARAGE
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | HERNAN ARREOLA |
| Corrections Issued | 9/13/2021 | HERNAN ARREOLA |
| Quality Review Completed | 9/16/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/17/2021 | APPLICANT |
| Applicant returned to address corrections | 11/29/2021 | HERNAN ARREOLA |
| Plan Check Approved | 4/1/2022 | HERNAN ARREOLA |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 9/13/2024 | KIRK SANDERS |
| CofO in Progress | 9/13/2024 | KIRK SANDERS |
| Permit Finaled | 10/8/2024 | RICHARD STEINBACH |
| CofO Issued | 10/8/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/8/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/18/2021 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2022 | ANDREW SLUSSER |
| Sewer availability | Cleared | 1/7/2022 | ANDREW SLUSSER |
| Specific Plan | Cleared | 1/13/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 2/10/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | ANTHONY MAINEZ |
| Excavation more than 5-ft deep | Cleared | 4/1/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | M G Partners Inc; Lic. No.: 886387-B | 761 E DAILY DR #140 CAMARILLO, CA 93010 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: C58475 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 7/18/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Approved | JEREMY TODD |
| PLUMBING-Rough | 7/18/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 7/21/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | BEN MOLSTAD |
| Insulation | 9/19/2023 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 9/19/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 10/11/2023 | Approved | BEN MOLSTAD |
| Final | 7/29/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 7/29/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 7/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 7/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 8/22/2024 | Conditional Approval | KIRK SANDERS |
| Service/Power Release | 8/22/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 8/22/2024 | Approved | KIRK SANDERS |