1676-1678 E 109TH ST 90059
Certificate Information: 1676-1678 E 109TH ST 90059
- Application / Permit
- 21010-10000-04085
- Plan Check / Job No.
- B21LA14827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/31/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 8/31/2021 | SAI KHUM |
| Applicant returned to address corrections | 10/19/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/8/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 12/1/2021 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| Issued | 7/26/2022 | APPLICANT |
| CofO in Progress | 5/15/2023 | JOHN KLARIN |
| CofO in Progress | 5/15/2023 | JOHN KLARIN |
| CofO in Progress | 5/15/2023 | DANIEL ORRANTE |
| No Progress | 5/15/2023 | DANIEL ORRANTE |
| CofO in Progress | 5/15/2023 | DANIEL ORRANTE |
| CofO in Progress | 5/17/2023 | JAMES CHAVEZ |
| Permit Finaled | 5/22/2023 | ANSON MAGLASANG |
| CofO Issued | 5/22/2023 | ANSON MAGLASANG |
| Permit Finaled | 5/22/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | WALLIE JONG |
| Highway dedication | Cleared | 9/10/2021 | WALLIE JONG |
| Permit | Cleared | 9/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/25/2021 | ROBERT DUFF |
| Sewer availability | Cleared | 10/8/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 10/18/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | CELINA MORENO |
| Trees in Parkway | Cleared | 10/21/2021 | ADALBERTO VERA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/23/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 10/14/2022 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 10/17/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 12/30/2022 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 12/30/2022 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 12/30/2022 | Approved | JOHN KLARIN |
| Insulation | 1/10/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 1/18/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 1/18/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 3/20/2023 | Conditional Approval | JOHN KLARIN |
| ELECTRICAL-Final | 4/21/2023 | Approved | JAMES CHAVEZ |
| Final | 4/21/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 4/21/2023 | Approved | JAMES CHAVEZ |
| HVAC-Final | 4/21/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 4/21/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 4/21/2023 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 4/21/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 4/24/2023 | Approved | JAMES CHAVEZ |
| Final | 5/12/2023 | Not Ready for Inspection | JOHN KLARIN |