1527 W 254TH ST 90710

Certificate Information: 1527 W 254TH ST 90710

Application / Permit
21010-10000-04082
Plan Check / Job No.
B21LA14821
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) Garage/Workshop into ADU per GCS 65852.2 and 65852.22
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 3/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 HERNAN ARREOLA
Corrections Issued 8/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/23/2021 HERNAN ARREOLA
Plan Check Approved 8/27/2021 HERNAN ARREOLA
Issued 10/5/2021 APPLICANT
CofO in Progress 10/15/2022 EUGENE CASSIDY
CofO Issued 3/8/2023 ANSON MAGLASANG
Permit Finaled 3/8/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/16/2021 ERIK BEASLEY
Sewer availability Cleared 8/16/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 8/18/2021 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 11/17/2021 Partial Approval EUGENE CASSIDY
Sewer 11/17/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 1/11/2022 Partial Approval DAVID FEILER
Sewer 1/11/2022 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 1/18/2022 Approved ANSON MAGLASANG
Special/Order Compliance 1/18/2022 Partial Approval ANSON MAGLASANG
PLUMBING-Final 1/24/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/24/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Final 1/31/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 3/23/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 3/23/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 3/23/2022 Approved EUGENE CASSIDY
Wood Frame 3/23/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 4/22/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 4/22/2022 Approved EUGENE CASSIDY
Wood Frame 4/22/2022 Corrections Issued EUGENE CASSIDY
Deputy Drilled-In Anchors 5/4/2022 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 5/4/2022 Partial Approval EUGENE CASSIDY
Wood Frame 5/18/2022 Partial Approval EUGENE CASSIDY
Insulation 6/3/2022 Approved EUGENE CASSIDY
Deputy Wood Construction 6/9/2022 Partial Approval EUGENE CASSIDY
Drywall Nailing 6/14/2022 Approved EUGENE CASSIDY
Green Building Rough 6/14/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/14/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
Final 8/30/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/12/2022 Corrections Issued EUGENE CASSIDY
Final 9/12/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 9/12/2022 Approved EUGENE CASSIDY
HVAC-Final 9/12/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/12/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 9/12/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/16/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/16/2022 Approved EUGENE CASSIDY
Final 9/16/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 9/16/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved EUGENE CASSIDY
Special/Order Compliance 9/16/2022 Approved EUGENE CASSIDY
Final 9/22/2022 Corrections Issued EUGENE CASSIDY
Final 10/13/2022 OK to Issue CofO EUGENE CASSIDY