5043 N CARTWRIGHT AVE 91601

Certificate Information: 5043 N CARTWRIGHT AVE 91601

Application / Permit
21010-10000-04029
Plan Check / Job No.
B21LA14686
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD W/ ATTACHED 2 CAR GARAGE (FRONT)
Permit Issued
Issued on 2/14/2023
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 KHEDER ALRAZAA
Corrections Issued 9/1/2021 KHEDER ALRAZAA
Quality Review Completed 9/8/2021 JASON HEALEY
Building Plans Picked Up 9/11/2021 APPLICANT
Applicant returned to address corrections 4/20/2022 KHEDER ALRAZAA
Plan Check Approved 5/6/2022 KHEDER ALRAZAA
Issued 2/14/2023 APPLICANT
CofO in Progress 3/18/2026 GAREN HAYRAPETYAN
Permit Finaled 4/9/2026 RUBEN SALAS
CofO Issued 4/9/2026 RUBEN SALAS
Permit Finaled 4/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/2/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/2/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/2/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 12/3/2021 GILBERT URREA
Low Impact Development Cleared 2/5/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/8/2022 DAGOVERTO GUERRERO
Permit Cleared 4/8/2022 DAGOVERTO GUERRERO
Trees in Parkway Cleared 4/8/2022 ADALBERTO VERA

Contact Information

Contractor Advanced Construction; Lic. No.: 801955-B 4606 WILLIS AVE #307      SHERMAN OAKS, CA 91403
Engineer Mansuri,, Mehran; Lic. No.: C78614 14944 HESBY ST      SHERMAN OAKS, CA 91403

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/2/2023 Corrections Issued JOHN HAYES
Underground Mechanical 6/2/2023 Off-Hour Fees Due
Underground Mechanical 6/14/2023 Partial Approval DAVID MATSON
Footing/Foundation/Slab 6/22/2023 Off-Hour Fees Due
Footing/Foundation/Slab 6/27/2023 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 7/5/2023 Corrections Issued ROBERT GOLD
Green Building Rough 7/5/2023 Not Ready for Inspection ROBERT GOLD
Verify Sprinkler Sign Off 7/5/2023 Not Ready for Inspection ROBERT GOLD
Footing/Foundation/Slab 7/13/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 9/18/2023 Corrections Issued JOHN HAYES
Green Building Rough 9/18/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 9/18/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/25/2023 Corrections Issued JOHN HAYES
Green Building Rough 9/25/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 9/25/2023 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 9/26/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 10/2/2023 Partial Approval JOHN HAYES
Green Building Rough 10/2/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 10/2/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/2/2024 No Access for Inspection MISAEL ESPARZA
Green Building Rough 1/2/2024 No Access for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 1/2/2024 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 1/12/2024 Corrections Issued JOHN HAYES
Green Building Rough 1/12/2024 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 1/12/2024 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/22/2024 No Access for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 1/27/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 1/27/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 1/27/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 2/14/2024 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/14/2024 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 2/14/2024 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 2/14/2024 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 2/21/2024 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 2/29/2024 Conditional Approval DAVID MATSON
Deputy Wood Construction 3/19/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 4/2/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 4/9/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 4/15/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 4/15/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 4/18/2024 Corrections Issued JENNIFER RABUCHIN
Gas Test 4/18/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/18/2024 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/18/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 4/19/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/19/2024 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 4/25/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/29/2024 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/16/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval JOSE AVILA
HVAC-Rough 5/23/2024 Approved JOSE AVILA
PLUMBING-Rough 5/23/2024 Approved JOSE AVILA
Drywall Nailing 5/28/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/28/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 5/28/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/3/2024 Approved JOSE AVILA
Drywall Nailing 6/3/2024 Partial Approval JOSE AVILA
Special/Order Compliance 6/3/2024 Corrections Issued JOSE AVILA
Insulation 8/15/2024 Approved JOSE AVILA
Interior/Exterior Lathing 8/15/2024 Approved JOSE AVILA
Sewer 9/23/2024 Not Ready for Inspection JOSE AVILA
Sewer 9/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 9/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 9/30/2024 Corrections Issued JOSE AVILA
Underground Mechanical 10/3/2024 Partial Approval JOSE AVILA
Pre-Inspection 10/18/2024 Approved JOSE AVILA
Special/Order Compliance 3/13/2025 Partial Inspection JOSE AVILA
Special/Order Compliance 4/8/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 4/24/2025 Partial Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 6/23/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 7/7/2025 Corrections Issued JOSE AVILA
PLUMBING-Final 7/7/2025 Not Ready for Inspection JOSE AVILA
Drywall Nailing 8/25/2025 Approved JOSE AVILA
ELECTRICAL-Final 8/25/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 8/25/2025 Approved JOSE AVILA
Final 8/28/2025 Corrections Issued JOSE AVILA
Final 2/20/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 2/20/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/20/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 3/18/2026 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 3/18/2026 Approved GAREN HAYRAPETYAN
Service/Power Release 3/18/2026 Approved GAREN HAYRAPETYAN
Special/Order Compliance 4/1/2026 Partial Inspection ROBERTO PALACIOS-LOPEZ