2255 S CAMDEN AVE 90064
Certificate Information: 2255 S CAMDEN AVE 90064
- Application / Permit
- 21010-10000-03971
- Plan Check / Job No.
- B21LA14498
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING W/ ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | DANIEL YIP |
| Corrections Issued | 8/31/2021 | DANIEL YIP |
| Quality Review Completed | 9/2/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/7/2021 | APPLICANT |
| Applicant returned to address corrections | 11/29/2021 | DANIEL YIP |
| Applicant returned to address corrections | 12/17/2021 | DANIEL YIP |
| Plan Check Approved | 3/16/2022 | DANIEL YIP |
| Plan Check Approved | 6/22/2022 | DANIEL YIP |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 8/22/2024 | KIRK SANDERS |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
| CofO Issued | 9/7/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 10/1/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/29/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 11/29/2021 | DANIEL YIP |
| Trees in Parkway | Cleared | 12/1/2021 | ADALBERTO VERA |
| Specific Plan | Cleared | 12/21/2021 | PEDRO AYALA |
| Specific Plan | Cleared | 2/17/2022 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 2/23/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/1/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | DINAH GARIN |
| Sewer availability | Cleared | 3/7/2022 | DINAH GARIN |
Contact Information
| Architect | Mechur,, Ralph Steven; Lic. No.: C11683 | 3400 AIRPORT AVE 5 SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Davidson,, Randall Gale; Lic. No.: C67456 | 307 HIGHLAND DR LOS OSOS, CA 93402 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/23/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/5/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 4/12/2023 | Partial Approval | HERBERT GIRON |
| Sewer | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 5/16/2023 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 5/30/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 5/31/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/1/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 6/2/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/6/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 6/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/20/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/26/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/27/2023 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 6/27/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/3/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | JEREMY TODD |
| Green Building Rough | 7/7/2023 | Approved | JEREMY TODD |
| Deputy Steel/Welding | 7/10/2023 | Conditional Approval | JESUS PINEDA |
| Shower Pan | 7/10/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 7/19/2023 | Approved | JEREMY TODD |
| Insulation | 7/25/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 7/31/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 8/8/2023 | Approved | MEL KHACHATOURIAN |
| Service/Power Release | 2/1/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/27/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 3/11/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 3/20/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 3/22/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 5/31/2024 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 5/31/2024 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 5/31/2024 | Approved | JESUS PINEDA |
| Final | 6/6/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 6/6/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | JESUS PINEDA |
| Service/Power Release | 6/6/2024 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 7/25/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 7/25/2024 | Approved | TEMISTOCLES CAAL |
| Final | 8/21/2024 | OK to Issue CofO | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 8/21/2024 | Approved | KIRK SANDERS |