159 W 27TH ST 90007

Certificate Information: 159 W 27TH ST 90007

Application / Permit
21010-10000-03967
Plan Check / Job No.
B21LA14486
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
ONE STORY WAREHOUSE
Permit Issued
Issued on 4/26/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Green Plans Picked Up 8/18/2021 APPLICANT
Disabled Access Plans Picked Up 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 YOUNG KIM
Corrections Issued 9/3/2021 YOUNG KIM
Quality Review Completed 9/8/2021 KEN GILL
Building Plans Picked Up 9/9/2021 APPLICANT
Applicant returned to address corrections 9/15/2022 YOUNG KIM
Applicant returned to address corrections 2/8/2023 YOUNG KIM
Applicant returned to address corrections 4/13/2023 YOUNG KIM
Plan Check Approved 4/26/2023 YOUNG KIM
Issued 4/26/2023 APPLICANT
CofO in Progress 4/9/2025 JAMES POWERS
Permit Finaled 4/9/2025 ERNESTO CORRAL
CofO Issued 4/9/2025 ERNESTO CORRAL
Permit Finaled 4/9/2025 ERNESTO CORRAL

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/7/2022 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 7/19/2022 JEANIE LAM
Historic Resource Verification Cleared 9/13/2022 MAX LODER
Redevelopment Project Area Cleared 9/22/2022 GRACIELA ACOSTA
Green Code Cleared 9/27/2022 AARON COSTA
Low Impact Development Cleared 10/12/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/7/2022 JEANIE LAM
Sewer availability Cleared 12/8/2022 JEANIE LAM
Internal circulation Cleared 12/12/2022 COLLINS ALLAN
DAS Clearance Cleared 2/7/2023 YOUNG KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 5/19/2023 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/19/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/19/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 5/19/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Partial Approval JAMES POWERS
Green Building Rough 6/13/2023 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/13/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/13/2023 Not Ready for Inspection JAMES POWERS
Deputy Methane Barrier 8/11/2023 Partial Approval JAMES POWERS
Drywall Nailing 8/24/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Approved JAMES POWERS
METHANE-Final 8/24/2023 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 8/24/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/7/2023 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 9/13/2023 Approved JAMES POWERS
Footing/Foundation/Slab 9/27/2023 Partial Approval JAMES POWERS
METHANE-Barrier 9/27/2023 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 9/27/2023 Not Ready for Inspection JAMES POWERS
Insulation 10/4/2023 Not Ready for Inspection JAMES POWERS
Insulation 10/5/2023 Approved JAMES POWERS
Drywall Nailing 10/10/2023 Approved JAMES POWERS
Green Building Rough 10/10/2023 Approved JAMES POWERS
T-Bar Ceiling 12/13/2023 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 1/10/2024 Approved JAMES POWERS
METHANE-Final 1/10/2024 Not Ready for Inspection JAMES POWERS
Insulation 1/11/2024 Approved JAMES POWERS
T-Bar Ceiling 1/11/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/26/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/27/2024 Partial Approval JAMES POWERS
Final 11/19/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 11/19/2024 Approved JAMES POWERS
Green Building Final 11/19/2024 Approved JAMES POWERS
METHANE-Final 11/19/2024 Partial Approval JAMES POWERS
METHANE-Rough 11/19/2024 Approved JAMES POWERS
METHANE-Subgrade 11/19/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/19/2024 SGSOV No Gas JAMES POWERS
Smoke Detectors 11/19/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/19/2024 Approved JAMES POWERS
Wood Frame 11/19/2024 Not Ready for Inspection JAMES POWERS
Final 12/17/2024 OK for TCO JAMES POWERS
METHANE-Final 12/17/2024 Approved JAMES POWERS
METHANE-Rough 12/17/2024 Approved JAMES POWERS
Wood Frame 12/17/2024 Approved JAMES POWERS
Final 4/8/2025 OK to Issue CofO JAMES POWERS