159 W 27TH ST 90007
Certificate Information: 159 W 27TH ST 90007
- Application / Permit
- 21010-10000-03967
- Plan Check / Job No.
- B21LA14486
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- ONE STORY WAREHOUSE
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Green Plans Picked Up | 8/18/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | YOUNG KIM |
| Corrections Issued | 9/3/2021 | YOUNG KIM |
| Quality Review Completed | 9/8/2021 | KEN GILL |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| Applicant returned to address corrections | 9/15/2022 | YOUNG KIM |
| Applicant returned to address corrections | 2/8/2023 | YOUNG KIM |
| Applicant returned to address corrections | 4/13/2023 | YOUNG KIM |
| Plan Check Approved | 4/26/2023 | YOUNG KIM |
| Issued | 4/26/2023 | APPLICANT |
| CofO in Progress | 4/9/2025 | JAMES POWERS |
| Permit Finaled | 4/9/2025 | ERNESTO CORRAL |
| CofO Issued | 4/9/2025 | ERNESTO CORRAL |
| Permit Finaled | 4/9/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/7/2022 | RUEL COLE |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | JEANIE LAM |
| Historic Resource Verification | Cleared | 9/13/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 9/22/2022 | GRACIELA ACOSTA |
| Green Code | Cleared | 9/27/2022 | AARON COSTA |
| Low Impact Development | Cleared | 10/12/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/7/2022 | JEANIE LAM |
| Sewer availability | Cleared | 12/8/2022 | JEANIE LAM |
| Internal circulation | Cleared | 12/12/2022 | COLLINS ALLAN |
| DAS Clearance | Cleared | 2/7/2023 | YOUNG KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 5/19/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/19/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 5/19/2023 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 6/13/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 6/13/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 6/13/2023 | Not Ready for Inspection | JAMES POWERS |
| Deputy Methane Barrier | 8/11/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/24/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Approved | JAMES POWERS |
| METHANE-Final | 8/24/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 8/24/2023 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 9/7/2023 | Not Ready for Inspection | LARRY ARNICK |
| Interior/Exterior Lathing | 9/13/2023 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 9/27/2023 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 9/27/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Subgrade | 9/27/2023 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 10/4/2023 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 10/5/2023 | Approved | JAMES POWERS |
| Drywall Nailing | 10/10/2023 | Approved | JAMES POWERS |
| Green Building Rough | 10/10/2023 | Approved | JAMES POWERS |
| T-Bar Ceiling | 12/13/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Barrier | 1/10/2024 | Approved | JAMES POWERS |
| METHANE-Final | 1/10/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 1/11/2024 | Approved | JAMES POWERS |
| T-Bar Ceiling | 1/11/2024 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 3/26/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 3/27/2024 | Partial Approval | JAMES POWERS |
| Final | 11/19/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 11/19/2024 | Approved | JAMES POWERS |
| Green Building Final | 11/19/2024 | Approved | JAMES POWERS |
| METHANE-Final | 11/19/2024 | Partial Approval | JAMES POWERS |
| METHANE-Rough | 11/19/2024 | Approved | JAMES POWERS |
| METHANE-Subgrade | 11/19/2024 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 11/19/2024 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/19/2024 | Approved | JAMES POWERS |
| Wood Frame | 11/19/2024 | Not Ready for Inspection | JAMES POWERS |
| Final | 12/17/2024 | OK for TCO | JAMES POWERS |
| METHANE-Final | 12/17/2024 | Approved | JAMES POWERS |
| METHANE-Rough | 12/17/2024 | Approved | JAMES POWERS |
| Wood Frame | 12/17/2024 | Approved | JAMES POWERS |
| Final | 4/8/2025 | OK to Issue CofO | JAMES POWERS |